5654-5654 1/2 N CARTWRIGHT AVE 91601

Certificate Information: 5654-5654 1/2 N CARTWRIGHT AVE 91601

Application / Permit
25016-20000-13698
Plan Check / Job No.
B25VN11913
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
PROPOSED NONSTRUCT INT REMODEL TO CONVERT EX ATTACHED REC RM INTO ACCESSORY DWELLING UNIT PER GCS 66323(a)(3) WITHIN EX 3-STORY DUPLEX W/GARAGE. SEE COMMENTS.
Permit Issued
Issued on 7/15/2025
Issuing Office
Current Status
CofO Issued on 12/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2025 APPLICANT
Assigned to Plan Check Engineer 5/2/2025 HAYATO TSUCHIYA
Corrections Issued 5/3/2025 HAYATO TSUCHIYA
Building Plans Picked Up 5/7/2025 APPLICANT
Applicant returned to address corrections 5/19/2025 NAREG ATARIAN
Issued 7/15/2025 APPLICANT
CofO in Progress 11/20/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 12/2/2025 RUBEN SALAS
CofO Issued 12/2/2025 RUBEN SALAS
Permit Finaled 12/2/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/19/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/19/2025 LEE GUILBEAUX
Sewer availability Cleared 5/19/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 7/17/2025 No Access for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 7/17/2025 No Access for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 7/17/2025 No Access for Inspection JENNIFER RABUCHIN
Drywall Nailing 7/23/2025 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 10/17/2025 SGSOV Not Ready JOSE AVILA
Rough-Elec/Plmb/HVAC 10/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 11/4/2025 Approved JOSE AVILA
ELECTRICAL-Rough 11/5/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 11/5/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 11/5/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 11/7/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 11/7/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 11/7/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 11/7/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 11/7/2025 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 11/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 11/7/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 11/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 11/10/2025 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Service/Power Release 11/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 11/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 11/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 11/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 11/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 11/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 11/13/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 11/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 11/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 11/19/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Green Building Final 11/19/2025 Approved ROBERTO PALACIOS-LOPEZ