7748 N MARQUAND AVE 91304
Certificate Information: 7748 N MARQUAND AVE 91304
- Application / Permit
- 25016-20000-13090
- Plan Check / Job No.
- B25VN11367
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 6/24/2025
- Issuing Office
- Current Status
- Permit Finaled on 12/19/2025
Permit Application Status History
| Submitted | 4/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2025 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 5/2/2025 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 5/2/2025 | APPLICANT |
| Plan Check Approved | 6/24/2025 | ALEC MOUSAKHANIAN |
| Issued | 6/24/2025 | APPLICANT |
| Permit Finaled | 12/18/2025 | CHRIS CHRISTENSEN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/5/2025 | ALEXANDER HELFER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/19/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Deputy Drilled-In Anchors | 9/19/2025 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 9/19/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Excavation/Setback/Form/Re-Bar | 9/19/2025 | Corrections Issued | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 9/19/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| PLUMBING-Rough | 9/19/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 9/24/2025 | Partial Approval | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 9/24/2025 | Approved | JEFFREY HARTLINE |
| Excavation/Setback/Form/Re-Bar | 9/24/2025 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 9/24/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 9/24/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 9/26/2025 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 9/26/2025 | Partial Approval | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 11/4/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 11/4/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Special/Order Compliance | 11/4/2025 | Corrections Issued | JEFFREY HARTLINE |
| PLUMBING-Rough | 11/6/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 11/14/2025 | Partial Approval | JEFFREY HARTLINE |
| Shower Pan | 11/14/2025 | Approved | JEFFREY HARTLINE |
| Final | 12/18/2025 | Permit Finaled | CHRIS CHRISTENSEN |
| Smoke Detectors | 12/18/2025 | Approved | CHRIS CHRISTENSEN |