2757 S OVERLAND AVE 90064
Certificate Information: 2757 S OVERLAND AVE 90064
- Application / Permit
- 25016-20000-13081
- Plan Check / Job No.
- B25VN11356
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL EXISTING 2 STORY HOUSE. REMOVE LOAD BEARING WALLS PER PLAN. ADD/REPLACE WINDOWS AND EXTERIOR DOOR OF DIFFERENT SIZES. COMPLY WITH DEPARTMENT ORDER effective date 06/30/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 7/15/2025
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 12/9/2025
Permit Application Status History
| Submitted | 4/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2025 | JESSE ARELLANO |
| Corrections Issued | 4/29/2025 | JESSE ARELLANO |
| Building Plans Picked Up | 5/2/2025 | APPLICANT |
| Plan Check Approved | 7/15/2025 | GIOVANNY CHAVEZ |
| Issued | 7/15/2025 | APPLICANT |
| Permit Finaled | 12/5/2025 | PETER RUBIO |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/1/2025 | LANNY MERRICK |
| Sewer availability | Cleared | 5/8/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/28/2025 | JESUS CISNEROS |
| Miscellaneous | Cleared | 7/10/2025 | DIANA RENTERIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/22/2025 | Approved | PETER RUBIO |
| PLUMBING-Rough | 7/28/2025 | Approved | PETER RUBIO |
| ELECTRICAL-Rough | 8/11/2025 | Approved | PETER RUBIO |
| HVAC-Rough | 8/11/2025 | Approved | PETER RUBIO |
| Shower Pan | 8/11/2025 | Approved | PETER RUBIO |
| BUILDING-Rough-Frame | 8/15/2025 | Approved | PETER RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2025 | Approved | PETER RUBIO |
| Insulation | 8/15/2025 | Approved | PETER RUBIO |
| Interior/Exterior Lathing | 8/27/2025 | Approved | PETER RUBIO |
| Drywall Nailing | 9/8/2025 | Approved | PETER RUBIO |
| ELECTRICAL-Final | 12/1/2025 | Approved | PETER RUBIO |
| Gas Test | 12/1/2025 | Approved | PETER RUBIO |
| PLUMBING-Final | 12/1/2025 | Approved | PETER RUBIO |
| Final | 12/5/2025 | Permit Finaled | PETER RUBIO |
| HVAC-Final | 12/5/2025 | Approved | PETER RUBIO |
| SGSOV-Seismic Gas S/O Valve | 12/5/2025 | SGSOV Approved | PETER RUBIO |
| Smoke Detectors | 12/5/2025 | Approved | PETER RUBIO |