11140 N CABRIOLE AVE 91326
Certificate Information: 11140 N CABRIOLE AVE 91326
- Application / Permit
- 25016-20000-12986
- Plan Check / Job No.
- B25VN11337
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL TO (E) SFD, ENCLOSE AND CONVERT AND (E) ATTACHED PATIO COVER TO BE PART OF SFD, REFRAME ROOF, CREATE CEILING MORE THAN 14' IN HEIGHT ( 177.7 SF) AND REPAIR ROOF OF (E) 1-STORY SFD DUE TO FIRE DAMAGE PER ENGINEERING
- Permit Issued
- Issued on 6/5/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2025 | ALFRED RAMIREZ |
| Corrections Issued | 5/1/2025 | ALFRED RAMIREZ |
| Quality Review Completed | 5/2/2025 | STEVEN KIM |
| Building Plans Picked Up | 5/5/2025 | APPLICANT |
| Applicant returned to address corrections | 6/3/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 6/5/2025 | ALFRED RAMIREZ |
| Issued | 6/5/2025 | APPLICANT |
| CofO in Progress | 3/4/2026 | DAVID SCANTLIN |
| Permit Finaled | 3/7/2026 | MICHAEL PELHAM |
| CofO Issued | 3/7/2026 | MICHAEL PELHAM |
| Permit Finaled | 3/7/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 6/4/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 6/4/2025 | SAFA JAVANMARDI |
| Grading Pre-Inspection | Cleared | 6/6/2025 | GERMAN RODRIGUEZ MENDOZA |
Contact Information
| Contractor | Aaa Remediation; Lic. No.: 983777-B | 4549 WHITE OAK PL ENCINO, CA 91316 |
| Engineer | Azarbin,, Hamid; Lic. No.: C64515 | 22655 COVELLO ST WEST HILLS, CA 91307 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/14/2025 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 8/21/2025 | Partial Approval | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2025 | Partial Approval | DAVID SCANTLIN |
| Underground Mechanical | 9/3/2025 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 10/14/2025 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 10/14/2025 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 10/14/2025 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 10/27/2025 | Partial Approval | ARUTYUN MADATYAN |
| Insulation | 11/4/2025 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 11/12/2025 | No Access for Inspection | DAVID SCANTLIN |
| Drywall Nailing | 11/19/2025 | Approved | DAVID SCANTLIN |
| Shower Pan | 12/17/2025 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 2/25/2026 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 2/25/2026 | Approved | DAVID SCANTLIN |
| Final | 2/25/2026 | Corrections Issued | DAVID SCANTLIN |
| HVAC-Final | 2/25/2026 | Approved | DAVID SCANTLIN |
| MERV13>=Final | 2/25/2026 | Approved | DAVID SCANTLIN |
| MERV13>=Rough | 2/25/2026 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 2/25/2026 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 2/25/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 2/25/2026 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 3/3/2026 | Approved | DAVID SCANTLIN |
| Final | 3/3/2026 | OK to Issue CofO | DAVID SCANTLIN |
| HVAC-Final | 3/3/2026 | Approved | DAVID SCANTLIN |
| Service/Power Release | 3/3/2026 | Approved | DAVID SCANTLIN |