4139 N HAYVENHURST AVE 91436
Certificate Information: 4139 N HAYVENHURST AVE 91436
- Application / Permit
- 25016-20000-12744
- Plan Check / Job No.
- B25VN11140
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) TWO-STORY ACCESSORY LIVING QUARTERS TO NEW ACCESSORY DWELLING UNIT (2511 SQ FT) PER GC 66323(a)(1). NO STRUCTURAL WORK.
- Permit Issued
- Issued on 5/27/2025
- Issuing Office
- Current Status
- CofO Issued on 9/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 4/29/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/30/2025 | APPLICANT |
| Issued | 5/27/2025 | APPLICANT |
| CofO in Progress | 9/10/2025 | JOHN KIDWELL |
| Permit Finaled | 9/24/2025 | JOHN JANSON |
| CofO Issued | 9/24/2025 | JOHN JANSON |
| Permit Finaled | 9/24/2025 | JOHN JANSON |
Permit Application Clearance Information
| ZA Case | Cleared | 4/30/2025 | JASON CHAN |
| Address approval | Cleared | 5/5/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 5/5/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/11/2025 | Approved | JOHN KIDWELL |
| Final | 6/11/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Pre-Inspection | 6/11/2025 | Partial Approval | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 6/11/2025 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 6/11/2025 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 6/11/2025 | Approved | JOHN KIDWELL |
| Final | 6/18/2025 | Partial Inspection | JOHN KIDWELL |
| Grounding or Bonding | 6/18/2025 | Partial Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Approved | JOHN KIDWELL |
| Final | 7/31/2025 | Conditional Approval | JOHN KIDWELL |
| Final | 8/27/2025 | Corrections Issued | JOHN KIDWELL |
| Final | 9/4/2025 | OK to Issue CofO | JOHN KIDWELL |