7413 N DEMPSEY AVE 91406
Certificate Information: 7413 N DEMPSEY AVE 91406
- Application / Permit
- 25016-20000-12709
- Plan Check / Job No.
- B25VN11112
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE AND STORAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 66323(a)(1).
- Permit Issued
- Issued on 5/26/2025
- Issuing Office
- Current Status
- CofO Issued on 3/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2025 | GIOVANNY CHAVEZ |
| Corrections Issued | 4/26/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 5/13/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 5/15/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 5/22/2025 | MIROOSH KHACHATOORIAN |
| Issued | 5/26/2025 | APPLICANT |
| CofO in Progress | 2/11/2026 | GAREN HAYRAPETYAN |
| Permit Finaled | 3/3/2026 | RUBEN SALAS |
| Permit Finaled | 3/3/2026 | RUBEN SALAS |
| CofO Issued | 3/3/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/30/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 4/30/2025 | MICHAEL BROWN |
| Construction near power lines | Cleared | 5/1/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Markarian Setrag; Lic. No.: 832632-B | , |
| Contractor | Pampa Investment Inc; Lic. No.: 832632-B | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/9/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Pre-Inspection | 7/14/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 8/8/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Sewer | 8/8/2025 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 10/8/2025 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 10/8/2025 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 10/14/2025 | Approved | WAYNE REGESTER |
| HVAC-Rough | 10/14/2025 | Approved | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2025 | Approved | JACK KARGODORIAN |
| Wood Frame | 10/27/2025 | Approved | JACK KARGODORIAN |
| Insulation | 11/5/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 11/5/2025 | Partial Approval | MICHAEL CORTEZ |
| Drywall Nailing | 11/12/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 12/1/2025 | Approved | WILLIAM WREN |
| Shower Pan | 12/1/2025 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 2/6/2026 | Approved | GAREN HAYRAPETYAN |
| Final | 2/6/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 2/6/2026 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 2/6/2026 | Approved | GAREN HAYRAPETYAN |
| MERV13>=Final | 2/6/2026 | Approved | GAREN HAYRAPETYAN |
| MERV13>=Rough | 2/6/2026 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 2/6/2026 | SGSOV Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 2/6/2026 | Approved | GAREN HAYRAPETYAN |
| Final | 2/11/2026 | OK to Issue CofO | GAREN HAYRAPETYAN |