4293-4293 1/2 N TUJUNGA AVE 91604
Certificate Information: 4293-4293 1/2 N TUJUNGA AVE 91604
- Application / Permit
- 25016-20000-11825
- Plan Check / Job No.
- B25VN10427
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT PORTION OF (E) GARAGE ATTACHED TO EXISTING DUPLEX TO ACCESSORY DWELLING UNIT AS PER GC 66323(a)(3) , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/13/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 5/13/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2025 | RARES BODEA |
| Corrections Issued | 4/22/2025 | RARES BODEA |
| Quality Review Completed | 4/24/2025 | STEVEN KIM |
| Building Plans Picked Up | 4/25/2025 | APPLICANT |
| Plan Check Approved | 5/8/2025 | RARES BODEA |
| Issued | 5/13/2025 | APPLICANT |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 4/30/2025 | KORNEL LELEA |
| Address approval | Cleared | 5/1/2025 | JESUS LUNA |
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2025 | JESUS LUNA |
| Sewer availability | Cleared | 5/1/2025 | JESUS LUNA |
| "Q" conditions | Cleared | 5/2/2025 | NATHAN ROMINE |
| ZI | Cleared | 5/2/2025 | NATHAN ROMINE |
Contact Information
| Contractor | Onward Builders Llc; Lic. No.: 1084275-B | 750 N SAN VICENTE BLVD STE 800 WEST HOLLYWOOD, CA 90069 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| HVAC-Rough | 6/30/2025 | Corrections Issued | JAVIER RAMOS JR |
| Pre-Inspection | 6/30/2025 | Partial Approval | JAVIER RAMOS JR |
| Special/Order Compliance | 6/30/2025 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/11/2025 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2025 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 7/11/2025 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Rough | 7/11/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/11/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/23/2025 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/23/2025 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2025 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 7/23/2025 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 7/23/2025 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 7/23/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/29/2025 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Rough | 7/29/2025 | Approved | JUAN VALENZUELA |
| Insulation | 7/29/2025 | Approved | JUAN VALENZUELA |
| Shower Pan | 7/29/2025 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 8/1/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/1/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 9/2/2025 | Approved | JAVIER RAMOS JR |
| Final | 9/2/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 9/2/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 9/2/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 9/2/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 9/2/2025 | SGSOV Not Required | JAVIER RAMOS JR |
| Smoke Detectors | 9/2/2025 | Approved | JAVIER RAMOS JR |