2553-2555 W 5TH ST 90057
Certificate Information: 2553-2555 W 5TH ST 90057
- Application / Permit
- 25016-20000-11549
- Plan Check / Job No.
- B25VN10174
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT (e) COVERED PATIO TO (N) ADU PER GCS 66323(a)(1) AND CONDITIONED RECREATION ROOM. INTERIOR REMODEL OF DUPLEX. CONVERT (E) GARAGE TO NEW BEDROOM FOR 2553 W 5TH ST BLDG COMPLY WITH DEPARTMENT ORDER effective date 02/10/2025. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 5/30/2025
- Issuing Office
- Metro
- Current Status
- Issued on 5/30/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2025 | JESSE ARELLANO |
| Corrections Issued | 4/23/2025 | JESSE ARELLANO |
| Building Plans Picked Up | 4/25/2025 | APPLICANT |
| Applicant returned to address corrections | 5/23/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 5/28/2025 | SERGIO MUNIZ |
| Plan Check Approved | 5/29/2025 | ARAMIK SHAHMIRZAIAN |
| Issued | 5/30/2025 | APPLICANT |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 5/21/2025 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 5/22/2025 | YASMINE BASHIRI |
| Address approval | Cleared | 5/23/2025 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2025 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 5/23/2025 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 5/23/2025 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| THOMAS WILLIS, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| JEFFREY CHRISTIAN, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| FERMIN RUBIO, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| JACOB SEGURA, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| CLAUDIO MORENO, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK RUDE, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/20/2025 | Approved | FERMIN RUBIO |
| Footing/Foundation/Slab | 7/15/2025 | Corrections Issued | FERMIN RUBIO |
| Rough-Elec/Plmb/HVAC | 7/15/2025 | Not Ready for Inspection | FERMIN RUBIO |
| Footing/Foundation/Slab | 7/30/2025 | Not Ready for Inspection | FERMIN RUBIO |
| ELECTRICAL-Rough | 8/1/2025 | Not Ready for Inspection | FERMIN RUBIO |
| Footing/Foundation/Slab | 8/1/2025 | Approved | FERMIN RUBIO |
| PLUMBING-Rough | 8/1/2025 | Not Ready for Inspection | FERMIN RUBIO |
| BUILDING-Rough-Frame | 9/11/2025 | Corrections Issued | FERMIN RUBIO |
| ELECTRICAL-Rough | 9/11/2025 | Corrections Issued | FERMIN RUBIO |
| Green Building Rough | 9/11/2025 | Not Ready for Inspection | FERMIN RUBIO |
| HVAC-Rough | 9/11/2025 | Corrections Issued | FERMIN RUBIO |
| METHANE-Rough | 9/11/2025 | Not Ready for Inspection | FERMIN RUBIO |
| PLUMBING-Rough | 9/11/2025 | Corrections Issued | FERMIN RUBIO |
| BUILDING-Rough-Frame | 10/15/2025 | No Access for Inspection | FERMIN RUBIO |
| ELECTRICAL-Rough | 10/15/2025 | No Access for Inspection | FERMIN RUBIO |
| Green Building Rough | 10/15/2025 | No Access for Inspection | FERMIN RUBIO |
| METHANE-Rough | 10/15/2025 | No Access for Inspection | FERMIN RUBIO |
| PLUMBING-Rough | 10/15/2025 | No Access for Inspection | FERMIN RUBIO |
| BUILDING-Rough-Frame | 10/21/2025 | Corrections Issued | FERMIN RUBIO |
| ELECTRICAL-Rough | 10/21/2025 | Conditional Approval | FERMIN RUBIO |
| Green Building Rough | 10/21/2025 | Not Ready for Inspection | FERMIN RUBIO |
| METHANE-Rough | 10/21/2025 | Not Ready for Inspection | FERMIN RUBIO |
| PLUMBING-Rough | 10/21/2025 | Corrections Issued | FERMIN RUBIO |
| BUILDING-Rough-Frame | 10/29/2025 | Not Ready for Inspection | FERMIN RUBIO |
| ELECTRICAL-Rough | 10/29/2025 | Approved | FERMIN RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2025 | Not Ready for Inspection | FERMIN RUBIO |
| Gas Test | 10/29/2025 | Not Ready for Inspection | FERMIN RUBIO |
| Green Building Rough | 10/29/2025 | Not Ready for Inspection | FERMIN RUBIO |
| METHANE-Rough | 10/29/2025 | Not Ready for Inspection | FERMIN RUBIO |
| PLUMBING-Rough | 10/29/2025 | Not Ready for Inspection | FERMIN RUBIO |
| PLUMBING-Rough | 11/13/2025 | Conditional Approval | FERMIN RUBIO |
| Shower Pan | 11/13/2025 | Approved | FERMIN RUBIO |
| Insulation | 12/4/2025 | Partial Approval | JACOB SEGURA |
| Interior/Exterior Lathing | 12/4/2025 | Partial Approval | JACOB SEGURA |
| Shower Pan | 12/4/2025 | Not Ready for Inspection | JACOB SEGURA |
| Insulation | 12/12/2025 | Corrections Issued | FERMIN RUBIO |
| BUILDING-Rough-Frame | 4/15/2026 | Corrections Issued | FERMIN RUBIO |
| Drywall Nailing | 4/15/2026 | Conditional Approval | FERMIN RUBIO |
| Insulation | 4/15/2026 | Conditional Approval | FERMIN RUBIO |
| BUILDING-Rough-Frame | 6/15/2026 | Corrections Issued | FERMIN RUBIO |
| Order to Comply | 6/15/2026 | Not Required | FERMIN RUBIO |