2519 1/2 S 5TH AVE 90018
Certificate Information: 2519 1/2 S 5TH AVE 90018
- Application / Permit
- 25016-20000-11374
- Plan Check / Job No.
- B25VN10054
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 9/8/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 4/22/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/28/2025 | APPLICANT |
| Plan Check Approved | 7/25/2025 | GIOVANNY CHAVEZ |
| Issued | 9/8/2025 | APPLICANT |
| CofO in Progress | 4/7/2026 | JUSTIN HAWLEY |
| CofO Issued | 4/9/2026 | DEROLD HAUFF |
| Permit Finaled | 4/9/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/22/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/22/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 5/22/2025 | RYAN CASTRO |
| Construction near power lines | Cleared | 5/30/2025 | ENRIQUE ACOSTA |
| HPOZ | Cleared | 7/25/2025 | DEBORAH MCGILL |
Contact Information
| Architect | Saikley,, Scott; Lic. No.: C32819 | 2519 5TH AVENUE LOS ANGELES, CA 90018 |
| Contractor | Eleven Eleven Construction; Lic. No.: 986326-B | 6362 W 83RD ST LOS ANGELES, CA 90045 |
| Engineer | Ibarra,, Marco A; Lic. No.: C74010 | 2596 MISSION ST STE 330A SAN MARINO, CA 91108 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/12/2025 | Approved | JUSTIN HAWLEY |
| Deputy Drilled-In Anchors | 9/25/2025 | Conditional Approval | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 9/25/2025 | Corrections Issued | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 10/6/2025 | Approved | JUSTIN HAWLEY |
| Grounding or Bonding | 10/14/2025 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 10/14/2025 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2025 | Corrections Issued | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 10/24/2025 | Corrections Issued | JUSTIN HAWLEY |
| Underground Mechanical | 10/24/2025 | Approved | JUSTIN HAWLEY |
| Deputy Wood Construction | 10/28/2025 | Conditional Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 10/29/2025 | Approved | JUSTIN HAWLEY |
| MERV13>=Rough | 10/29/2025 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 10/29/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 12/17/2025 | Approved | JUSTIN HAWLEY |
| Insulation | 12/17/2025 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 12/17/2025 | Partial Approval | JUSTIN HAWLEY |
| Drywall Nailing | 1/29/2026 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 1/29/2026 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 4/2/2026 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 4/2/2026 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 4/2/2026 | Not Ready for Inspection | JUSTIN HAWLEY |
| HVAC-Final | 4/2/2026 | Not Ready for Inspection | JUSTIN HAWLEY |
| MERV13>=Final | 4/2/2026 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 4/2/2026 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 4/2/2026 | SGSOV Not Ready | JUSTIN HAWLEY |
| Verify Rec and Parks Fee Memo | 4/2/2026 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 4/7/2026 | Approved | JUSTIN HAWLEY |
| Final | 4/7/2026 | OK to Issue CofO | JUSTIN HAWLEY |
| Green Building Final | 4/7/2026 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 4/7/2026 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 4/7/2026 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 4/7/2026 | SGSOV Not Required | JUSTIN HAWLEY |
| Smoke Detectors | 4/7/2026 | Approved | JUSTIN HAWLEY |
| Verify Rec and Parks Fee Memo | 4/7/2026 | Approved | JUSTIN HAWLEY |