8633-8635 W LE BERTHON ST 91040

Certificate Information: 8633-8635 W LE BERTHON ST 91040

Application / Permit
25016-20000-11349
Plan Check / Job No.
B25VN10020
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. CONVERSION OF THE EXISTING GARAGE AND PORTION OF ATTACHED ENCLOSED PATIO TO JADU (496 SF) PER GC 66323(a)(1) AND 66333
Permit Issued
Issued on 7/29/2025
Issuing Office
Current Status
CofO Issued on 2/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2025 APPLICANT
Assigned to Plan Check Engineer 4/15/2025 FERNANDO FLORES
Corrections Issued 4/16/2025 FERNANDO FLORES
Applicant returned to address corrections 6/23/2025 FERNANDO FLORES
Applicant returned to address corrections 7/11/2025 ADAM HEGAZI
Plan Check Approved 7/25/2025 ADAM HEGAZI
Issued 7/29/2025 APPLICANT
CofO in Progress 1/12/2026 NICHOLAS TROWBRIDGE
Permit Finaled 2/3/2026 RUBEN SALAS
CofO Issued 2/3/2026 RUBEN SALAS
Permit Finaled 2/3/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/18/2025 COLIN LOREDO
Sewer availability Cleared 4/18/2025 COLIN LOREDO
Grading Pre-Inspection Cleared 4/18/2025 GERMAN RODRIGUEZ MENDOZA
Eng Process Fee Ord 176,300 Cleared 6/4/2025 COLIN LOREDO
Flood clearance Cleared 6/18/2025 ELYSE GREPO

Contact Information

Contractor Universal Nava Electric; Lic. No.: 1012939-B       ,
Engineer Truong,, Phong; Lic. No.: C70784 20439 E CRESTLINE DRIVE      WALNUT, CA 91789

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/11/2025 Corrections Issued WILLIAM WREN
PLUMBING-Rough 9/3/2025 Partial Approval WILLIAM WREN
Sewer 9/3/2025 Approved WILLIAM WREN
Footing/Foundation/Slab 9/10/2025 Approved WILLIAM WREN
Reinforced Concrete Frame 9/10/2025 Not Ready for Inspection WILLIAM WREN
BUILDING-Rough-Frame 10/2/2025 Not Ready for Inspection WILLIAM WREN
FLOOD-Proofing Certificate 10/2/2025 Not Ready for Inspection WILLIAM WREN
Gas Test 10/2/2025 Approved WILLIAM WREN
Green Building Rough 10/2/2025 Not Ready for Inspection WILLIAM WREN
Interior/Exterior Lathing 10/2/2025 Partial Approval WILLIAM WREN
Rough-Elec/Plmb/HVAC 10/2/2025 Approved WILLIAM WREN
Wood Frame 10/2/2025 Not Ready for Inspection WILLIAM WREN
Wood Frame 10/6/2025 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Approved WAYNE REGESTER
Insulation 10/7/2025 Approved WAYNE REGESTER
Interior/Exterior Lathing 10/7/2025 Approved WAYNE REGESTER
Wood Frame 10/7/2025 Approved WAYNE REGESTER
Floor/Roof Diaphrgm/Shear Wall 10/8/2025 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/10/2025 Not Ready for Inspection WAYNE REGESTER
Wood Frame 10/10/2025 Not Ready for Inspection WAYNE REGESTER
Drywall Nailing 10/21/2025 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 12/29/2025 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Final 12/29/2025 Approved JACK KARGODORIAN
FLOOD-Proofing Certificate 12/29/2025 Not Ready for Inspection JACK KARGODORIAN
Final 12/29/2025 Corrections Issued JACK KARGODORIAN
Green Building Final 12/29/2025 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 12/29/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 12/29/2025 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 12/29/2025 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 1/9/2026 Approved NICHOLAS TROWBRIDGE
FLOOD-Proofing Certificate 1/9/2026 Approved NICHOLAS TROWBRIDGE
Final 1/9/2026 OK to Issue CofO NICHOLAS TROWBRIDGE
Green Building Final 1/9/2026 Approved NICHOLAS TROWBRIDGE