17613 W BURTON ST 91325

Certificate Information: 17613 W BURTON ST 91325

Application / Permit
25016-20000-11022
Plan Check / Job No.
B25VN09718
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
ePlan Remodel detached garage, raise ceiling hegiht, and replace roof
Permit Issued
Issued on 10/6/2025
Issuing Office
Current Status
CofO Issued on 5/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/17/2025 APPLICANT
Assigned to Plan Check Engineer 4/22/2025 NAREG ATARIAN
Corrections Issued 4/22/2025 NAREG ATARIAN
Applicant returned to address corrections 5/9/2025 NAREG ATARIAN
Applicant returned to address corrections 8/22/2025 NAREG ATARIAN
Plan Check Approved 8/28/2025 NAREG ATARIAN
Issued 10/6/2025 APPLICANT
CofO in Progress 4/29/2026 MICHAEL CORTEZ
CofO Issued 5/28/2026 RUBEN SALAS
Permit Finaled 5/28/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/6/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 6/9/2025 SAFA JAVANMARDI
Construction near power lines Cleared 7/25/2025 ENRIQUE ACOSTA

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: C93095 15755 SATICOY ST APT#306      VAN NUYS, CA 91406
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: NA93095       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/23/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Pre-Inspection 10/23/2025 Partial Inspection GAREN HAYRAPETYAN
Deputy Drilled-In Anchors 10/29/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 10/30/2025 Approved OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 11/4/2025 Corrections Issued GAREN HAYRAPETYAN
Deputy Reinf. Concrete 11/5/2025 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 11/6/2025 Approved GAREN HAYRAPETYAN
Deputy Reinf. Concrete 11/7/2025 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 3/4/2026 Approved KIRK SANDERS
Special/Order Compliance 3/4/2026 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 3/11/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/27/2026 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 3/27/2026 Approved JENNIFER RABUCHIN
Green Building Rough 3/27/2026 Approved JENNIFER RABUCHIN
Underground Mechanical 3/27/2026 Approved JENNIFER RABUCHIN
MERV13>=Rough 3/31/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/21/2026 Approved KIRK SANDERS
Final 4/21/2026 Corrections Issued KIRK SANDERS
HVAC-Final 4/21/2026 Approved KIRK SANDERS
PLUMBING-Final 4/21/2026 Approved KIRK SANDERS
BUILDING-Rough-Frame 4/28/2026 Approved MICHAEL CORTEZ
Final 4/28/2026 OK to Issue CofO MICHAEL CORTEZ
Green Building Final 4/28/2026 Approved MICHAEL CORTEZ
SGSOV-Seismic Gas S/O Valve 4/28/2026 SGSOV Not Required MICHAEL CORTEZ
Smoke Detectors 4/28/2026 Approved MICHAEL CORTEZ