910 W BLOOM WALK 101C 90089
Certificate Information: 910 W BLOOM WALK 101C 90089
- Application / Permit
- 25016-20000-10336
- Plan Check / Job No.
- B25VN09242
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- ePlan: Strutural support for mechanical equipment of room 101C on the ground floor of the building.
- Permit Issued
- Issued on 10/13/2025
- Issuing Office
- Current Status
- Permit Finaled on 4/1/2026
Permit Application Status History
| Submitted | 4/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2025 | TSE MING HUANG |
| Corrections Issued | 4/8/2025 | TSE MING HUANG |
| Plan Check Approved | 5/20/2025 | TSE MING HUANG |
| Plan Check Approved | 10/7/2025 | JOHNPAUL ISIP |
| Issued | 10/13/2025 | APPLICANT |
| Permit Finaled | 3/25/2026 | ALFREDO LOPEZ |
Permit Application Clearance Information
| Historic monument | Cleared | 4/9/2025 | LAMBERT GIESSINGER |
| Tenant Habitability Plan | Cleared | 4/9/2025 | KORNEL LELEA |
| Specific Plan | Cleared | 4/10/2025 | MANERI ROMAN |
Contact Information
| Architect | Dontje,, Jason Alan; Lic. No.: NA32176 | , |
| Contractor | Vancrest Construction Corp; Lic. No.: 393800-B | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 3/25/2026 | Permit Finaled | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/25/2026 | SGSOV Not Required | ALFREDO LOPEZ |
| Smoke Detectors | 3/25/2026 | Approved | ALFREDO LOPEZ |