812 E 91ST ST 90002

Certificate Information: 812 E 91ST ST 90002

Application / Permit
25016-20000-10318
Plan Check / Job No.
B25VN09216
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL EXISTING 2- STORY SFD: @ 2ND FLR - COMPLETE INT REMODEL. CONVERT EX ONE BEDRM W/ ONE BATH RM INTO TWO BEDRMS & ONE BATH RM. @ 1ST FLR - REMODEL EX TWO BEDRMS & TWO BATHRMS. ALL WORK PER ENGR DESIGN.
Permit Issued
Issued on 5/23/2025
Issuing Office
Current Status
Issued on 5/23/2025

Permit Application Status History

Submitted 4/4/2025 APPLICANT
Assigned to Plan Check Engineer 4/11/2025 HAYATO TSUCHIYA
Corrections Issued 4/14/2025 HAYATO TSUCHIYA
Building Plans Picked Up 4/17/2025 APPLICANT
Issued 5/23/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/29/2025 LEE GUILBEAUX
Sewer availability Cleared 4/29/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/29/2025 LEE GUILBEAUX

Contact Information

Contractor Evergreen Construction Group Inc; Lic. No.: 998238-B 6444 BELLINGHAM AVE #204      NORTH HOLLYWOOD, CA 91606
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/5/2025 Corrections Issued JOHN QUINTANILLA
BUILDING-Rough-Frame 10/17/2025 Not Ready for Inspection JOHN QUINTANILLA
Wood Frame 10/17/2025 Partial Inspection JOHN QUINTANILLA
Wood Frame 11/26/2025 Not Ready for Inspection JOHN QUINTANILLA
Wood Frame 12/3/2025 Corrections Issued JOHN QUINTANILLA
BUILDING-Rough-Frame 12/5/2025 Corrections Issued JOHN QUINTANILLA
BUILDING-Rough-Frame 12/9/2025 Not Ready for Inspection JOHN QUINTANILLA
Wood Frame 12/11/2025 Conditional Approval JOHN QUINTANILLA
HVAC-Rough 2/5/2026 Approved JOHN QUINTANILLA
PLUMBING-Rough 2/5/2026 Partial Approval JOHN QUINTANILLA
Interior/Exterior Lathing 2/9/2026 Approved ENRIQUE MIRELES
Shower Pan 2/9/2026 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 2/24/2026 Conditional Approval JOHN QUINTANILLA
ELECTRICAL-Rough 3/2/2026 Corrections Issued SALVADOR MARTINEZ
Drywall Nailing 3/11/2026 Partial Approval MICHAEL LEWIS
ELECTRICAL-Rough 3/11/2026 Approved MICHAEL LEWIS
Final 4/22/2026 Not Ready for Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 4/22/2026 SGSOV Not Ready JOHN QUINTANILLA
Smoke Detectors 4/22/2026 Not Ready for Inspection JOHN QUINTANILLA
Final 4/23/2026 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 4/23/2026 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 4/23/2026 Approved MICHAEL LEWIS