8039-8041 N ALLOTT AVE 91402

Certificate Information: 8039-8041 N ALLOTT AVE 91402

Application / Permit
25016-20000-09695
Plan Check / Job No.
B25VN08742
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1).
Permit Issued
Issued on 4/9/2025
Issuing Office
Valley
Current Status
CofO Issued on 9/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2025 APPLICANT
Assigned to Plan Check Engineer 4/4/2025 ARTIN ZARUKIAN
Corrections Issued 4/5/2025 ARTIN ZARUKIAN
Building Plans Picked Up 4/8/2025 APPLICANT
Plan Check Approved 4/9/2025 NAREG ATARIAN
Issued 4/9/2025 APPLICANT
CofO in Progress 9/4/2025 VINCENT HANLEY
CofO Issued 9/18/2025 RUBEN SALAS
Permit Finaled 9/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/7/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 4/7/2025 SAFA JAVANMARDI
Sewer availability Cleared 4/7/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/2/2025 Partial Approval VINCENT HANLEY
Sewer 5/2/2025 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 5/7/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 5/9/2025 Approved MICHEL ABAJAN
Sewer 5/9/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 6/11/2025 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 6/11/2025 Approved VINCENT HANLEY
Gas Test 6/11/2025 Approved VINCENT HANLEY
Green Building Rough 6/11/2025 Approved VINCENT HANLEY
HVAC-Rough 6/11/2025 Approved VINCENT HANLEY
PLUMBING-Rough 6/11/2025 Approved VINCENT HANLEY
Deputy Wood Construction 6/25/2025 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 6/27/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/27/2025 Approved VINCENT HANLEY
Insulation 6/27/2025 Approved VINCENT HANLEY
Drywall Nailing 7/9/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 7/9/2025 Approved VINCENT HANLEY
Shower Pan 7/9/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 9/3/2025 Approved VINCENT HANLEY
Final 9/3/2025 OK to Issue CofO VINCENT HANLEY
Green Building Final 9/3/2025 Approved VINCENT HANLEY
HVAC-Final 9/3/2025 Approved VINCENT HANLEY
PLUMBING-Final 9/3/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/3/2025 SGSOV Approved VINCENT HANLEY
Service/Power Release 9/3/2025 Approved VINCENT HANLEY
Smoke Detectors 9/3/2025 Approved VINCENT HANLEY