7900-7902 N FARRALONE AVE 91304
Certificate Information: 7900-7902 N FARRALONE AVE 91304
- Application / Permit
- 25016-20000-09566
- Plan Check / Job No.
- B25VN08637
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Convert attached garage to Junior ADU per GC 66323(a)(1) and 66333. Remove doors inside the SFD. All work per WFPP
- Permit Issued
- Issued on 8/18/2025
- Issuing Office
- Current Status
- Issued on 8/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2025 | NAREG ATARIAN |
| Corrections Issued | 4/8/2025 | NAREG ATARIAN |
| Applicant returned to address corrections | 7/18/2025 | NAREG ATARIAN |
| Applicant returned to address corrections | 8/1/2025 | NAREG ATARIAN |
| Applicant returned to address corrections | 8/12/2025 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 8/13/2025 | NAREG ATARIAN |
| No Progress | 8/15/2025 | NAREG ATARIAN |
| Plan Check Approved | 8/15/2025 | NAREG ATARIAN |
| Issued | 8/18/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/8/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/8/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 5/8/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/20/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/29/2025 | Partial Inspection | JON MCHUGH |
| Footing/Foundation/Slab | 10/7/2025 | Partial Approval | HENRY KIM |
| PLUMBING-Rough | 10/7/2025 | Partial Approval | HENRY KIM |
| Sewer | 10/7/2025 | Corrections Issued | HENRY KIM |
| Sewer | 10/9/2025 | Approved | GEVORK IPCHYAN |
| Deputy Drilled-In Anchors | 12/3/2025 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 12/4/2025 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 1/21/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| Green Building Rough | 1/21/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 1/29/2026 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 1/29/2026 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 2/4/2026 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 2/24/2026 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 2/24/2026 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 2/24/2026 | Approved | JEFFREY HARTLINE |
| Insulation | 4/1/2026 | Approved | JEFFREY HARTLINE |
| Shower Pan | 4/1/2026 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 4/24/2026 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 5/7/2026 | Partial Approval | JEFFREY HARTLINE |