8775-8777 N TYRONE AVE 91402

Certificate Information: 8775-8777 N TYRONE AVE 91402

Application / Permit
25016-20000-09549
Plan Check / Job No.
B25VN08634
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan CONVERT EXISTING 2-CAR GARAGE TO JADU
Permit Issued
Issued on 5/19/2025
Issuing Office
Current Status
CofO Issued on 12/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2025 APPLICANT
Assigned to Plan Check Engineer 4/4/2025 NEHEMIAS RAMOS
Corrections Issued 4/5/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 5/6/2025 NEHEMIAS RAMOS
Plan Check Approved 5/9/2025 NEHEMIAS RAMOS
Issued 5/19/2025 APPLICANT
CofO in Progress 11/5/2025 VINCENT HANLEY
CofO Issued 12/18/2025 RUBEN SALAS
Permit Finaled 12/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/26/2025 LEE GUILBEAUX
Sewer availability Cleared 4/26/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/26/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/27/2025 LEE GUILBEAUX

Contact Information

Contractor Herrera Home Services; Lic. No.: 963198-B       ,
Engineer Contreras,, Humberto; Lic. No.: C83240 10614 PARISE DR      WHITTIER, CA 90604

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/6/2025 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 6/10/2025 Approved VINCENT HANLEY
PLUMBING-Rough 6/10/2025 Partial Approval VINCENT HANLEY
Sewer 6/10/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 7/8/2025 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 7/8/2025 Approved VINCENT HANLEY
Green Building Rough 7/8/2025 Approved VINCENT HANLEY
HVAC-Rough 7/8/2025 Approved VINCENT HANLEY
PLUMBING-Rough 7/8/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 7/17/2025 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 7/17/2025 Approved KEVIN BERBERYAN
Insulation 7/17/2025 Approved KEVIN BERBERYAN
Drywall Nailing 7/25/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 7/25/2025 Partial Approval MICHAEL CORTEZ
ELECTRICAL-Final 10/14/2025 Approved MATTHEW NELSON
Final 10/14/2025 Corrections Issued MATTHEW NELSON
Green Building Final 10/14/2025 Corrections Issued MATTHEW NELSON
HVAC-Final 10/14/2025 Corrections Issued MATTHEW NELSON
PLUMBING-Final 10/14/2025 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/14/2025 SGSOV Approved MATTHEW NELSON
Smoke Detectors 10/14/2025 Approved MATTHEW NELSON
Final 11/3/2025 OK to Issue CofO VINCENT HANLEY
Green Building Final 11/3/2025 Approved VINCENT HANLEY
HVAC-Final 11/3/2025 Approved VINCENT HANLEY