9011 W SAWYER ST 90035

Certificate Information: 9011 W SAWYER ST 90035

Application / Permit
25016-20000-09417
Plan Check / Job No.
B25VN08609
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). NFPA-13D SPRINKLER REQUIRED THRU OUT
Permit Issued
Issued on 5/30/2025
Issuing Office
Valley
Current Status
CofO Issued on 5/22/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/28/2025 APPLICANT
Assigned to Plan Check Engineer 4/3/2025 JEROME MAGAT PALMA
Corrections Issued 4/4/2025 JEROME MAGAT PALMA
Building Plans Picked Up 4/7/2025 APPLICANT
Applicant returned to address corrections 5/12/2025 ARAMIK SHAHMIRZAIAN
Applicant returned to address corrections 5/22/2025 ISIS ARGUETA
Issued 5/30/2025 APPLICANT
CofO in Progress 5/18/2026 ASHLEY THOMPSON
Permit Finaled 5/22/2026 RICHARD STEINBACH
CofO Issued 5/22/2026 RICHARD STEINBACH
Permit Finaled 5/22/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 4/21/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 4/21/2025 CINDY QI
Sewer availability Cleared 4/21/2025 CINDY QI
Construction near power lines Cleared 5/2/2025 WALTER RAMIREZ

Contact Information

Contractor Norman Construction; Lic. No.: 535530-B 17614 SUPERIOR STREET      NORTHRIDGE, CA 91325
Engineer Shachar,, Shaul Shkory; Lic. No.: C29686 18208 EMELITA ST      TARZANA, CA 91356

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/10/2025 Partial Approval ASHLEY THOMPSON
PLUMBING-Rough 6/10/2025 Partial Approval ASHLEY THOMPSON
Footing/Foundation/Slab 6/24/2025 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 9/26/2025 Corrections Issued SEAN HAUPT
ELECTRICAL-Rough 9/26/2025 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 9/26/2025 Approved SEAN HAUPT
Green Building Rough 9/26/2025 Corrections Issued SEAN HAUPT
HVAC-Rough 9/26/2025 Approved SEAN HAUPT
METHANE-Rough 9/26/2025 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 9/26/2025 Approved SEAN HAUPT
BUILDING-Rough-Frame 10/6/2025 Approved EVAN COOPER
Green Building Rough 10/6/2025 Approved EVAN COOPER
Insulation 10/6/2025 Approved EVAN COOPER
Interior/Exterior Lathing 10/6/2025 Partial Approval EVAN COOPER
METHANE-Rough 10/6/2025 Approved EVAN COOPER
Verify Sprinkler Sign Off 10/6/2025 Approved EVAN COOPER
Drywall Nailing 10/20/2025 Approved EVAN COOPER
Interior/Exterior Lathing 10/20/2025 Approved EVAN COOPER
ELECTRICAL-Final 3/3/2026 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Final 5/11/2026 Not Ready for Inspection ASHLEY THOMPSON
Final 5/11/2026 Not Ready for Inspection ASHLEY THOMPSON
Green Building Final 5/11/2026 Approved ASHLEY THOMPSON
HVAC-Final 5/11/2026 Approved ASHLEY THOMPSON
PLUMBING-Final 5/11/2026 Corrections Issued ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 5/11/2026 SGSOV Not Required ASHLEY THOMPSON
Smoke Detectors 5/11/2026 Approved ASHLEY THOMPSON
ELECTRICAL-Final 5/15/2026 Approved ASHLEY THOMPSON
Final 5/15/2026 OK to Issue CofO ASHLEY THOMPSON
PLUMBING-Final 5/15/2026 Approved ASHLEY THOMPSON