3834 1/2 W ALOHA ST 90027

Certificate Information: 3834 1/2 W ALOHA ST 90027

Application / Permit
25016-20000-09075
Plan Check / Job No.
B25VN08301
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT UNDER FLOOR AREA OF (E) 2-STORY DUPLEX INTO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)and(e).
Permit Issued
Issued on 5/14/2025
Issuing Office
Valley
Current Status
Issued on 5/14/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/26/2025 APPLICANT
Assigned to Plan Check Engineer 4/2/2025 ARTIN ZARUKIAN
Corrections Issued 4/3/2025 ARTIN ZARUKIAN
Building Plans Picked Up 4/11/2025 APPLICANT
Plan Check Approved 5/13/2025 NAREG ATARIAN
Issued 5/14/2025 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/22/2025 CELINA MORENO
BHO/Hillside ordinance Cleared 4/22/2025 CELINA MORENO
BHO/Hillside ordinance Cleared 4/22/2025 CELINA MORENO
Sewer availability Cleared 4/22/2025 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 4/29/2025 CELINA MORENO
Address approval Cleared 5/1/2025 CELINA MORENO
Grading Pre-Inspection Cleared 5/13/2025 ROBERT PINA

Contact Information

Contractor B & R Creative Builders Inc; Lic. No.: 969864-B 6820 LA TIJERA BLVD STE 111      LOS ANGELES, CA 90045
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/2/2025 Approved ENRIQUE MIRELES
Deputy Drilled-In Anchors 6/5/2025 Approved ENRIQUE MIRELES
Deputy Drilled-In Anchors 6/18/2025 Approved ENRIQUE MIRELES
PLUMBING-Rough 7/7/2025 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 7/18/2025 Approved BRENDAN MORELLI
Underground Mechanical 7/18/2025 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 8/6/2025 Approved ENRIQUE MIRELES
Green Building Rough 8/6/2025 Approved ENRIQUE MIRELES
Pre-Inspection 12/16/2025 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 12/22/2025 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 12/22/2025 Approved ENRIQUE MIRELES
HVAC-Rough 12/22/2025 Approved ENRIQUE MIRELES
PLUMBING-Rough 12/22/2025 Approved ENRIQUE MIRELES
Shower Pan 1/13/2026 Approved ENRIQUE MIRELES