6650 N ST CLAIR AVE 91606
Certificate Information: 6650 N ST CLAIR AVE 91606
- Application / Permit
- 25016-20000-09042
- Plan Check / Job No.
- B25VN08281
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 18' X 20' DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1). ALL WORK PER WFPP.
- Permit Issued
- Issued on 4/18/2025
- Issuing Office
- Current Status
- Issued on 4/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2025 | ARAMIK SHAHMIRZAIAN |
| Corrections Issued | 3/26/2025 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 4/18/2025 | HAYATO TSUCHIYA |
| Issued | 4/18/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/28/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 3/28/2025 | BIAINA HARITUNIAN |
| Historic Resource Verification | Cleared | 4/3/2025 | YASMINE BASHIRI |
| Redevelopment Project Area | Cleared | 4/3/2025 | YASMINE BASHIRI |
| ZI | Cleared | 4/3/2025 | YASMINE BASHIRI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 4/24/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 5/1/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 5/15/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 5/19/2025 | Approved | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 5/19/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2025 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/7/2025 | Corrections Issued | KEVIN BERBERYAN |
| HVAC-Rough | 7/7/2025 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 7/7/2025 | Corrections Issued | KEVIN BERBERYAN |
| Wood Frame | 7/7/2025 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 7/22/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 7/22/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 7/22/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 7/24/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 7/24/2025 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Rough | 7/24/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 8/27/2025 | Approved | WAYNE REGESTER |
| Wood Frame | 9/10/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 9/16/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 10/16/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 10/20/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 10/20/2025 | Approved | WAYNE REGESTER |
| Sewer | 10/30/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 4/21/2026 | Approved | WAYNE REGESTER |
| ELECTRICAL-Final | 4/21/2026 | Approved | WAYNE REGESTER |
| Final | 4/21/2026 | Corrections Issued | WAYNE REGESTER |
| Green Building Final | 4/21/2026 | Approved | WAYNE REGESTER |
| HVAC-Final | 4/21/2026 | Corrections Issued | WAYNE REGESTER |
| MERV13>=Final | 4/21/2026 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 4/21/2026 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 4/21/2026 | SGSOV Approved | WAYNE REGESTER |
| Smoke Detectors | 4/21/2026 | Approved | WAYNE REGESTER |
| ELECTRICAL-Final | 5/15/2026 | Approved | WAYNE REGESTER |
| Final | 5/15/2026 | Corrections Issued | WAYNE REGESTER |
| HVAC-Final | 5/15/2026 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 5/15/2026 | Approved | WAYNE REGESTER |