7413 N GLORIA AVE 91406
Certificate Information: 7413 N GLORIA AVE 91406
- Application / Permit
- 25016-20000-08963
- Plan Check / Job No.
- B25VN08219
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXISTING SINGLE-FAMILY DWELLING INTERIOR REMODEL TO ALSO INCLUDE THE KITCHEN WITH REMOVAL OF WALLS BETWEEN KITCHEN AND DINING ROOM
- Permit Issued
- Issued on 3/26/2025
- Issuing Office
- Current Status
- Issued on 3/26/2025
Permit Application Status History
| Submitted | 3/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2025 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 3/26/2025 | ALEC MOUSAKHANIAN |
| Issued | 3/26/2025 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazarians,, Harmick; Lic. No.: C91232 | 9825 OSO AVE CHATSWORTH, CA 91311 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/17/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 4/17/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 4/17/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 4/17/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 4/22/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 4/22/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Rough | 4/22/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 4/22/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 4/24/2025 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 4/24/2025 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 4/24/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 4/24/2025 | Approved | JACK KARGODORIAN |
| Insulation | 4/28/2025 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 4/30/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 5/22/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 7/24/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 7/24/2025 | Partial Inspection | SALVADOR MARTINEZ |
| HVAC-Final | 7/24/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Final | 7/24/2025 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 7/24/2025 | SGSOV Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 7/24/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 7/29/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Smoke Detectors | 7/29/2025 | Corrections Issued | SALVADOR MARTINEZ |