5923-5927 N CORBIN AVE 91356
Certificate Information: 5923-5927 N CORBIN AVE 91356
- Application / Permit
- 25016-20000-08539
- Plan Check / Job No.
- B25VN07843
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT AND REC ROOM TO ACCESSORY DWELLNG UNIT PER GCS 66323(a)(1) and 66333.
- Permit Issued
- Issued on 4/3/2025
- Issuing Office
- Current Status
- CofO Issued on 10/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 3/29/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 4/2/2025 | APPLICANT |
| Issued | 4/3/2025 | APPLICANT |
| CofO in Progress | 10/21/2025 | JON MCHUGH |
| Permit Finaled | 10/21/2025 | JOHN JANSON |
| CofO Issued | 10/21/2025 | JOHN JANSON |
| Permit Finaled | 10/21/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/1/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/1/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 4/1/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/22/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 4/25/2025 | Partial Approval | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 5/12/2025 | Corrections Issued | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 5/12/2025 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 5/19/2025 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 5/19/2025 | Approved | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 5/19/2025 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 5/23/2025 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 5/23/2025 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 5/23/2025 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 5/29/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 5/29/2025 | Approved | JON MCHUGH |
| Green Building Rough | 5/29/2025 | Approved | JON MCHUGH |
| Insulation | 5/29/2025 | Approved | JON MCHUGH |
| Drywall Nailing | 6/4/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 6/4/2025 | Approved | JON MCHUGH |
| Final | 7/11/2025 | Corrections Issued | JON MCHUGH |
| Green Building Final | 7/11/2025 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 7/11/2025 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 7/11/2025 | Approved | JON MCHUGH |
| Final | 9/12/2025 | Corrections Issued | MORRIS JACKSON |
| Green Building Final | 9/12/2025 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 9/12/2025 | SGSOV Approved | MORRIS JACKSON |
| Final | 9/30/2025 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Final | 10/20/2025 | Approved | JON MCHUGH |
| Final | 10/20/2025 | OK to Issue CofO | JON MCHUGH |
| HVAC-Final | 10/20/2025 | Approved | JON MCHUGH |
| PLUMBING-Final | 10/20/2025 | Approved | JON MCHUGH |