5923-5927 N CORBIN AVE 91356

Certificate Information: 5923-5927 N CORBIN AVE 91356

Application / Permit
25016-20000-08539
Plan Check / Job No.
B25VN07843
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT AND REC ROOM TO ACCESSORY DWELLNG UNIT PER GCS 66323(a)(1) and 66333.
Permit Issued
Issued on 4/3/2025
Issuing Office
Current Status
CofO Issued on 10/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2025 APPLICANT
Assigned to Plan Check Engineer 3/28/2025 ARTIN ZARUKIAN
Corrections Issued 3/29/2025 ARTIN ZARUKIAN
Building Plans Picked Up 4/2/2025 APPLICANT
Issued 4/3/2025 APPLICANT
CofO in Progress 10/21/2025 JON MCHUGH
Permit Finaled 10/21/2025 JOHN JANSON
CofO Issued 10/21/2025 JOHN JANSON
Permit Finaled 10/21/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/1/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/1/2025 LEE GUILBEAUX
Sewer availability Cleared 4/1/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/1/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/22/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 4/25/2025 Partial Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 5/12/2025 Corrections Issued JON MCHUGH
Rough-Elec/Plmb/HVAC 5/12/2025 Corrections Issued JON MCHUGH
BUILDING-Rough-Frame 5/19/2025 Corrections Issued JON MCHUGH
PLUMBING-Rough 5/19/2025 Approved JON MCHUGH
Rough-Elec/Plmb/HVAC 5/19/2025 Corrections Issued JON MCHUGH
BUILDING-Rough-Frame 5/23/2025 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 5/23/2025 Not Ready for Inspection JON MCHUGH
HVAC-Rough 5/23/2025 Approved JON MCHUGH
BUILDING-Rough-Frame 5/29/2025 Approved JON MCHUGH
ELECTRICAL-Rough 5/29/2025 Approved JON MCHUGH
Green Building Rough 5/29/2025 Approved JON MCHUGH
Insulation 5/29/2025 Approved JON MCHUGH
Drywall Nailing 6/4/2025 Approved JON MCHUGH
Interior/Exterior Lathing 6/4/2025 Approved JON MCHUGH
Final 7/11/2025 Corrections Issued JON MCHUGH
Green Building Final 7/11/2025 Not Ready for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 7/11/2025 SGSOV Not Ready JON MCHUGH
Smoke Detectors 7/11/2025 Approved JON MCHUGH
Final 9/12/2025 Corrections Issued MORRIS JACKSON
Green Building Final 9/12/2025 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Approved MORRIS JACKSON
Final 9/30/2025 Corrections Issued JON MCHUGH
ELECTRICAL-Final 10/20/2025 Approved JON MCHUGH
Final 10/20/2025 OK to Issue CofO JON MCHUGH
HVAC-Final 10/20/2025 Approved JON MCHUGH
PLUMBING-Final 10/20/2025 Approved JON MCHUGH