12240 W HESBY ST 91607
Certificate Information: 12240 W HESBY ST 91607
- Application / Permit
- 25016-20000-08522
- Plan Check / Job No.
- B25VN07833
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: NEW 308.81 ADDITION OF A DEN TO (E) SFD, INTERIOR REMODEL THROUGHOUT
- Permit Issued
- Issued on 4/11/2025
- Issuing Office
- Current Status
- CofO Issued on 12/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2025 | LUISANGEL VALENZUELA |
| Corrections Issued | 3/28/2025 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 4/2/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 4/3/2025 | LUISANGEL VALENZUELA |
| No Progress | 4/7/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 4/7/2025 | LUISANGEL VALENZUELA |
| No Progress | 4/10/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 4/10/2025 | LUISANGEL VALENZUELA |
| Issued | 4/11/2025 | APPLICANT |
| CofO in Progress | 11/10/2025 | JAVIER RAMOS JR |
| Permit Finaled | 12/19/2025 | RUBEN SALAS |
| CofO Issued | 12/19/2025 | RUBEN SALAS |
| Permit Finaled | 12/19/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2025 | COLIN LOREDO |
| Miscellaneous | Cleared | 4/1/2025 | ASHLEY RODARTE |
| Roof/Waste drainage to street | Cleared | 4/1/2025 | COLIN LOREDO |
| Specific Plan | Cleared | 4/2/2025 | JOANNA MARROQUIN |
| ZI | Cleared | 4/2/2025 | JOANNA MARROQUIN |
| ZI | Cleared | 4/2/2025 | JOANNA MARROQUIN |
Contact Information
| Contractor | Speciality Builders Inc; Lic. No.: 1001098-B | 23679 CALABASAS RD STE 1013 CALABASAS, CA 91304 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/24/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 4/24/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Excavation/Setback/Form/Re-Bar | 4/28/2025 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 4/28/2025 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Insulation | 5/5/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 6/10/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 6/10/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 6/10/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 6/10/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 6/13/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 6/17/2025 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 6/23/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 10/9/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 10/9/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 10/9/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 10/9/2025 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/9/2025 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 10/9/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 11/10/2025 | OK to Issue CofO | JAVIER RAMOS JR |