15901 W OLDEN ST 91342

Certificate Information: 15901 W OLDEN ST 91342

Application / Permit
25016-20000-08490
Plan Check / Job No.
B25VN07827
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
RENOVATE AND CHANGE OF USEAN EXISTING ONE STORY STORAGE BUILDING TO OFFICE. INCLUDES SELECTIVE DEMOLITION OF EXISTING EXTERIOR WALL FOR NEW WINDOWS & DOORS AND INTERIOR OUT TO COORDINATE WITH NEW PLAN. NEW INTERIOR CONSTRUCTION TO INCLUDE NEW OPEN WORK SPACES AND ENCLOSED OFFICES
Permit Issued
Issued on 6/9/2025
Issuing Office
Current Status
CofO Issued on 4/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2025 APPLICANT
Assigned to Plan Check Engineer 3/27/2025 FARSHAD ALIMOHAMADI
Assigned to Zoning Architect 3/27/2025 NEVRIK NAVASARTIAN
Corrections Issued 4/1/2025 FARSHAD ALIMOHAMADI
Quality Review Completed 4/7/2025 HERNAN ARREOLA
Applicant returned to address corrections 5/30/2025 FARSHAD ALIMOHAMADI
Plan Check Approved 6/1/2025 FARSHAD ALIMOHAMADI
Issued 6/9/2025 APPLICANT
CofO in Progress 4/2/2026 ANDREW DORSO
Permit Finaled 4/7/2026 JEFFREY DURAN
CofO Issued 4/7/2026 JEFFREY DURAN
Permit Finaled 4/7/2026 JEFFREY DURAN

Permit Application Clearance Information

City Hist. Cultural Monument Cleared 4/14/2025 LAMBERT GIESSINGER
"Q" conditions Cleared 4/15/2025 BRENNEN OBETO
ZA Case Cleared 4/15/2025 BRENNEN OBETO
ZA Case Cleared 4/15/2025 BRENNEN OBETO
Grading Pre-Inspection Cleared 4/15/2025 GERMAN RODRIGUEZ MENDOZA
Metro Rail approval Cleared 4/24/2025 JENNIFER SU
Metro Rail approval Cleared 4/24/2025 JENNIFER SU
Eng Process Fee Ord 176,300 Cleared 4/25/2025 DAVID PEREZ
Sewer availability Cleared 4/25/2025 DAVID PEREZ
DAS Clearance Cleared 5/12/2025 Pinank Patel
Zoning Plan Check Cleared 5/19/2025 Pinank Patel

Contact Information

Contractor Tutor Perini Corporation; Lic. No.: 92072-B 15901 OLDEN STREET      SYLMAR, CA 91342
Engineer Moore,, Claire; Lic. No.: S5134 126 CREST AVE      RICHMOND, CA 94810

Inspector Information

ANDREW DORSO, (818) 374-7520 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/12/2025 Partial Inspection ANDREW DORSO
Deputy Steel/Welding 6/30/2025 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 7/1/2025 Conditional Approval ANDREW DORSO
Deputy Drilled-In Anchors 7/2/2025 Conditional Approval ANDREW DORSO
Excavation/Setback/Form/Re-Bar 7/7/2025 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 7/7/2025 Partial Inspection ANDREW DORSO
Excavation/Setback/Form/Re-Bar 7/10/2025 Not Ready for Inspection ANDREW DORSO
Excavation/Setback/Form/Re-Bar 7/14/2025 Partial Inspection ANDREW DORSO
Deputy Steel/Welding 7/16/2025 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 7/17/2025 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 7/18/2025 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 7/21/2025 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 7/22/2025 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 7/23/2025 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 7/24/2025 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 7/25/2025 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 7/28/2025 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 7/29/2025 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 7/30/2025 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 7/31/2025 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 8/1/2025 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 8/4/2025 Partial Inspection ANDREW DORSO
Deputy Steel/Welding 9/3/2025 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 9/4/2025 Conditional Approval DEANDRE HOFFMAN
Insulation 9/4/2025 Partial Approval DEANDRE HOFFMAN
Light Gage Steel Frame 9/4/2025 Partial Approval DEANDRE HOFFMAN
Structural Steel Frame 9/4/2025 Partial Inspection DEANDRE HOFFMAN
Light Gage Steel Frame 9/9/2025 Partial Approval GREGORY POMISH
Drywall Nailing 9/10/2025 Partial Inspection GREGORY POMISH
Light Gage Steel Frame 9/11/2025 Not Ready for Inspection GREGORY POMISH
Drywall Nailing 9/15/2025 Not Ready for Inspection ANDREW DORSO
Drywall Nailing 9/17/2025 Not Ready for Inspection ANDREW DORSO
Drywall Nailing 9/18/2025 Partial Inspection ANDREW DORSO
Insulation 10/7/2025 Partial Inspection ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 10/15/2025 Not Ready for Inspection ANDREW DORSO
Light Gage Steel Frame 10/15/2025 Not Ready for Inspection ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 10/16/2025 Partial Inspection ANDREW DORSO
Deputy Drilled-In Anchors 10/23/2025 Conditional Approval ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 10/24/2025 Approved ANDREW DORSO
Light Gage Steel Frame 10/24/2025 Approved ANDREW DORSO
Wall Anchors 10/24/2025 Approved ANDREW DORSO
Insulation 10/29/2025 Approved ANDREW DORSO
Drywall Nailing 10/31/2025 Partial Inspection ANDREW DORSO
Drywall Nailing 11/4/2025 Partial Inspection ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 11/4/2025 Approved ANDREW DORSO
Final 4/1/2026 OK to Issue CofO ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 4/1/2026 SGSOV Approved ANDREW DORSO
Smoke Detectors 4/1/2026 Approved ANDREW DORSO
Wood Frame 4/1/2026 Approved ANDREW DORSO