17945 W CHATSWORTH ST 91344
Certificate Information: 17945 W CHATSWORTH ST 91344
- Application / Permit
- 25016-20000-08384
- Plan Check / Job No.
- B25VN07773
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- CHANGE OF USE FROM RETAIL TO RESTAURANT "COMPLY WITH DEPARTMENT ORDER effective date 06/12/2025. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 6/12/2025
- Issuing Office
- Current Status
- CofO Issued on 6/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 4/1/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/2/2025 | APPLICANT |
| Applicant returned to address corrections | 4/18/2025 | ISIS ARGUETA |
| Applicant returned to address corrections | 5/29/2025 | NAREG ATARIAN |
| Plan Check Approved | 6/12/2025 | ALEC MOUSAKHANIAN |
| Issued | 6/12/2025 | APPLICANT |
| CofO in Progress | 6/3/2026 | JASON WILSON |
| Permit Finaled | 6/5/2026 | JEFFREY DURAN |
| CofO Issued | 6/5/2026 | JEFFREY DURAN |
| Permit Finaled | 6/5/2026 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/20/2025 | CARLOS AGUILERA |
| Address approval | Cleared | 5/29/2025 | BIAINA HARITUNIAN |
| Food Service Establishment | Cleared | 6/2/2025 | STANLEY WING |
| "Q" conditions | Cleared | 6/9/2025 | DORIAN AGUILAR |
| ZA Case | Cleared | 6/9/2025 | DORIAN AGUILAR |
| Comm Cor/Mini-Mall | Cleared | 6/10/2025 | OLGA AYALA |
| Specific Plan | Cleared | 6/10/2025 | OLGA AYALA |
| Food establishment approval | Cleared | 6/11/2025 | LACDHS APPROVED |
Contact Information
| Architect | Kil,, Andrew Han; Lic. No.: C31817 | 13005 MESA VERDE WAY SYLMAR, CA 91342 |
| Contractor | Panchal Construction Company Inc; Lic. No.: 1112994-B | 8130 SANTA INEZ DRIVE BUENA PARK, CA 90620 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/17/2025 | Approved | BEHROUZ HASHEMI |
| Pre-Inspection | 12/2/2025 | Approved | BEHROUZ HASHEMI |
| Excavation/Setback/Form/Re-Bar | 12/3/2025 | Approved | BEHROUZ HASHEMI |
| Excavation/Setback/Form/Re-Bar | 12/17/2025 | Approved | BEHROUZ HASHEMI |
| Footing/Foundation/Slab | 12/17/2025 | Approved | BEHROUZ HASHEMI |
| Green Building Rough | 12/17/2025 | Approved | BEHROUZ HASHEMI |
| Wood Frame | 12/17/2025 | Not Ready for Inspection | BEHROUZ HASHEMI |
| Insulation | 2/9/2026 | Partial Approval | BEHROUZ HASHEMI |
| Light Gage Steel Frame | 2/9/2026 | Approved | BEHROUZ HASHEMI |
| Drywall Nailing | 2/11/2026 | Partial Approval | BEHROUZ HASHEMI |
| Insulation | 2/11/2026 | Approved | BEHROUZ HASHEMI |
| Drywall Nailing | 2/18/2026 | Approved | BEHROUZ HASHEMI |
| T-Bar Ceiling | 2/18/2026 | Not Ready for Inspection | BEHROUZ HASHEMI |
| Drywall Nailing | 3/2/2026 | Partial Inspection | EDWIN GREGORYONA |
| Special/Order Compliance | 3/2/2026 | Not Required | BEHROUZ HASHEMI |
| T-Bar Ceiling | 3/2/2026 | Approved | EDWIN GREGORYONA |
| Drywall Nailing | 3/4/2026 | Not Ready for Inspection | BRIAN KELLY |
| Drywall Nailing | 3/5/2026 | Approved | EDWIN GREGORYONA |
| Final | 5/6/2026 | Not Ready for Inspection | EDWIN GREGORYONA |
| Green Building Final | 5/6/2026 | Not Ready for Inspection | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 5/6/2026 | SGSOV Approved | EDWIN GREGORYONA |
| Smoke Detectors | 5/6/2026 | Approved | EDWIN GREGORYONA |
| T-Bar Ceiling | 5/6/2026 | Not Ready for Inspection | EDWIN GREGORYONA |
| Wood Frame | 5/6/2026 | Approved | EDWIN GREGORYONA |
| Final | 5/12/2026 | Not Ready for Inspection | EDWIN GREGORYONA |
| Green Building Final | 5/12/2026 | Not Ready for Inspection | EDWIN GREGORYONA |
| T-Bar Ceiling | 5/12/2026 | Not Ready for Inspection | EDWIN GREGORYONA |
| Final | 5/19/2026 | Partial Inspection | EDWIN GREGORYONA |
| Green Building Final | 5/19/2026 | Approved | EDWIN GREGORYONA |
| T-Bar Ceiling | 5/20/2026 | Approved | EDWIN GREGORYONA |
| T-Bar Ceiling | 5/21/2026 | Approved | EDWIN GREGORYONA |
| Final | 5/27/2026 | Conditional Approval | EDWIN GREGORYONA |
| T-Bar Ceiling | 5/27/2026 | Approved | EDWIN GREGORYONA |