2125-2127 N CYRIL AVE 90032

Certificate Information: 2125-2127 N CYRIL AVE 90032

Application / Permit
25016-20000-08311
Plan Check / Job No.
B25VN07705
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EX ATTACHED GARAGE INTO JR ACCESSORY DWELLING UNIT PER GCS 66323(a)(1) & 66333. CONSTRUCTION DESIGN PER ENGR.
Permit Issued
Issued on 5/2/2025
Issuing Office
Current Status
CofO Issued on 8/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2025 APPLICANT
Assigned to Plan Check Engineer 3/28/2025 HAYATO TSUCHIYA
Corrections Issued 3/29/2025 HAYATO TSUCHIYA
Building Plans Picked Up 4/2/2025 APPLICANT
Issued 5/2/2025 APPLICANT
CofO in Progress 8/19/2025 LILIANA PORTILLO
Permit Finaled 8/21/2025 DEROLD HAUFF
CofO Issued 8/21/2025 DEROLD HAUFF
Permit Finaled 8/21/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/3/2025 COLIN LOREDO
Sewer availability Cleared 4/3/2025 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 4/9/2025 COLIN LOREDO
Grading Pre-Inspection Cleared 4/9/2025 MICHAEL TEMPLE
"Q" conditions Cleared 4/17/2025 JAZMIN ROQUE

Contact Information

Contractor Estrada Plumbing & Remodeling Inc; Lic. No.: 814573-B 715 1/2 MILO TERRACE      LOS ANGELES, CA 90042
Engineer Dorier,, David Julien Miche; Lic. No.: S7064 950 S GRAND AVE 4TH FLOOR      LOS ANGELES, CA 90015

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/5/2025 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 6/12/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 6/23/2025 Partial Approval LILIANA PORTILLO
Wood Frame 6/23/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 7/1/2025 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 7/1/2025 Corrections Issued LILIANA PORTILLO
HVAC-Rough 7/1/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 7/1/2025 Corrections Issued LILIANA PORTILLO
Insulation 7/7/2025 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 7/10/2025 Approved LILIANA PORTILLO
Green Building Rough 7/10/2025 Approved LILIANA PORTILLO
Insulation 7/10/2025 Approved LILIANA PORTILLO
Interior/Exterior Lathing 7/10/2025 Partial Approval LILIANA PORTILLO
Rough-Elec/Plmb/HVAC 7/10/2025 Approved LILIANA PORTILLO
Drywall Nailing 7/14/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 7/14/2025 Approved ANTHONY RAMOS
Shower Pan 7/14/2025 Approved ANTHONY RAMOS
Final 8/7/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 8/7/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 8/7/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 8/7/2025 Approved ALIZAH MAYAGOITIA
Final 8/12/2025 OK to Issue CofO LILIANA PORTILLO
Green Building Final 8/12/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 8/12/2025 SGSOV Approved LILIANA PORTILLO