11432 N ACALA AVE 91340
Certificate Information: 11432 N ACALA AVE 91340
- Application / Permit
- 25016-20000-07480
- Plan Check / Job No.
- B25VN07158
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(1)
- Permit Issued
- Issued on 5/20/2025
- Issuing Office
- Current Status
- CofO Issued on 3/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2025 | DANIEL YIP |
| Corrections Issued | 3/20/2025 | DANIEL YIP |
| Applicant returned to address corrections | 5/15/2025 | KELVIN CHUONG |
| Applicant returned to address corrections | 5/17/2025 | KELVIN CHUONG |
| Plan Check Approved | 5/20/2025 | DANIEL YIP |
| Issued | 5/20/2025 | APPLICANT |
| CofO in Progress | 3/9/2026 | JENNIFER RABUCHIN |
| CofO Issued | 3/24/2026 | RUBEN SALAS |
| Permit Finaled | 3/24/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/2/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 4/2/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2025 | SAFA JAVANMARDI |
| Construction near power lines | Cleared | 5/9/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/25/2025 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 8/25/2025 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 8/25/2025 | Partial Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/3/2025 | Partial Approval | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 9/3/2025 | Approved | KEVIN BERBERYAN |
| MERV13>=Rough | 9/3/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 9/3/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 9/9/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 9/9/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/11/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 9/11/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 9/17/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/28/2025 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 12/18/2025 | Partial Approval | MICHEL ABAJAN |
| Final | 1/14/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/14/2026 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 1/14/2026 | Approved | JENNIFER RABUCHIN |
| Reinforced Masonry Frame | 1/14/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/14/2026 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 1/14/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 1/14/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 3/9/2026 | Approved | JENNIFER RABUCHIN |
| Final | 3/9/2026 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 3/9/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 3/9/2026 | Approved | JENNIFER RABUCHIN |
| Structural Steel Frame | 3/9/2026 | Approved | JENNIFER RABUCHIN |