10145-10147 N REMMET AVE 91311

Certificate Information: 10145-10147 N REMMET AVE 91311

Application / Permit
25016-20000-07314
Plan Check / Job No.
B25VN07049
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan CONVERT PORTION OF (E) REAR UNIT INTO (N) 2-STORY ACCESSORY DWELLING UNIT PER GCS 66323(a)(1).
Permit Issued
Issued on 6/11/2025
Issuing Office
Current Status
CofO Issued on 12/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2025 APPLICANT
Assigned to Plan Check Engineer 3/19/2025 ISIS ARGUETA
Corrections Issued 3/20/2025 ISIS ARGUETA
Applicant returned to address corrections 5/1/2025 ISIS ARGUETA
Applicant returned to address corrections 6/4/2025 NAREG ATARIAN
Plan Check Approved 6/7/2025 NAREG ATARIAN
No Progress 6/10/2025 NAREG ATARIAN
Plan Check Approved 6/10/2025 NAREG ATARIAN
No Progress 6/10/2025 NAREG ATARIAN
Plan Check Approved 6/10/2025 NAREG ATARIAN
Issued 6/11/2025 APPLICANT
CofO in Progress 11/17/2025 JEFFREY HARTLINE
Permit Finaled 12/1/2025 JOHN JANSON
CofO Issued 12/1/2025 JOHN JANSON
Permit Finaled 12/1/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/24/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/24/2025 RYAN CASTRO
Sewer availability Cleared 4/24/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: NA88029       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/24/2025 Partial Approval JEFFREY HARTLINE
Pre-Inspection 7/22/2025 Partial Approval JEFFREY HARTLINE
Pre-Inspection 7/29/2025 Partial Approval JEFFREY HARTLINE
Pre-Inspection 8/5/2025 Partial Approval JEFFREY HARTLINE
Pre-Inspection 9/24/2025 Partial Approval JEFFREY HARTLINE
Insulation 10/14/2025 Approved JEFFREY HARTLINE
Rough-Elec/Plmb/HVAC 10/14/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 10/31/2025 Approved JEFFREY HARTLINE
Final 10/31/2025 Corrections Issued JEFFREY HARTLINE
Smoke Detectors 10/31/2025 Approved JEFFREY HARTLINE
Final 11/17/2025 OK to Issue CofO JEFFREY HARTLINE