8913 N RATHBURN AVE 91325

Certificate Information: 8913 N RATHBURN AVE 91325

Application / Permit
25016-20000-06912
Plan Check / Job No.
B25VN06750
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN Convert existing detached garage to Accessory Dwelling Unit (436 SF) per GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 3/27/2025
Issuing Office
Current Status
CofO Issued on 6/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2025 APPLICANT
Assigned to Plan Check Engineer 3/17/2025 JOSE VELAZQUEZ
Corrections Issued 3/18/2025 JOSE VELAZQUEZ
Plan Check Approved 3/27/2025 JOSE VELAZQUEZ
Issued 3/27/2025 APPLICANT
CofO in Progress 6/2/2026 JACK KARGODORIAN
Permit Finaled 6/11/2026 JOHN JANSON
CofO Issued 6/11/2026 JOHN JANSON
Permit Finaled 6/11/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/21/2025 BIAINA HARITUNIAN
Sewer availability Cleared 3/21/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 3/24/2025 BIAINA HARITUNIAN
Hold Cleared 6/27/2025 TERESA RIVAS

Contact Information

Contractor Owner-Builder       ,
Engineer Tangonan,, Jeffrey Tolentino; Lic. No.: C83522 17770 CAPE JASMINE RD      CANYON COUNTRY, CA 91387

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/20/2025 Partial Inspection KRISTEN CAUSEY
Deputy Drilled-In Anchors 8/28/2025 Conditional Approval HENRY KIM
Deputy Drilled-In Anchors 8/29/2025 Conditional Approval DAVID SCANTLIN
Footing/Foundation/Slab 9/4/2025 Approved KRISTEN CAUSEY
Sewer 9/4/2025 Partial Approval KRISTEN CAUSEY
Wood Frame 10/17/2025 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 11/5/2025 Approved DAVID SCANTLIN
Green Building Rough 11/5/2025 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 11/5/2025 Approved DAVID SCANTLIN
Sewer 11/5/2025 Approved DAVID SCANTLIN
Drywall Nailing 12/15/2025 Approved KRISTEN CAUSEY
Gas Test 12/15/2025 Approved KRISTEN CAUSEY
Final 5/18/2026 Corrections Issued JACK KARGODORIAN
Green Building Final 5/18/2026 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 5/18/2026 SGSOV Not Ready JACK KARGODORIAN
Smoke Detectors 5/18/2026 Approved JACK KARGODORIAN
Final 5/26/2026 Corrections Issued JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 5/26/2026 SGSOV Not Ready JACK KARGODORIAN
Final 6/1/2026 OK to Issue CofO JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 6/1/2026 SGSOV Approved JACK KARGODORIAN