5125 E MERIDIAN ST 90042

Certificate Information: 5125 E MERIDIAN ST 90042

Application / Permit
25016-20000-06866
Plan Check / Job No.
B25VN06709
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) PATIO COVER TO BED AND BATH, REMODEL KITCHEN, REMOVE AND REPLACE ALL WINDOWS. "COMPLY WITH DEPARTMENT ORDER effective date 02/25/2025. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 4/29/2025
Issuing Office
Valley
Current Status
CofO Issued on 9/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2025 APPLICANT
Assigned to Plan Check Engineer 3/15/2025 ARTIN ZARUKIAN
Corrections Issued 3/15/2025 ARTIN ZARUKIAN
Building Plans Picked Up 3/19/2025 APPLICANT
Applicant returned to address corrections 4/10/2025 ALEC MOUSAKHANIAN
Plan Check Approved 4/25/2025 ISIS ARGUETA
Issued 4/29/2025 APPLICANT
CofO in Progress 8/18/2025 DANIEL DELACRUZ
Permit Finaled 9/15/2025 DANIEL SANCHEZ
CofO Issued 9/15/2025 DANIEL SANCHEZ
Permit Finaled 9/15/2025 DANIEL SANCHEZ

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/9/2025 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,
Engineer Asprer,, Anjero; Lic. No.: C91126 2708 FOOTHILL BLVD. #1006      LA CRESCENTA, CA 91214

Inspector Information

DANIEL DELACRUZ, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO SIERRA, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MINASSIANS, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/15/2025 Partial Approval DANIEL DELACRUZ
Deputy Drilled-In Anchors 6/3/2025 Conditional Approval DANIEL DELACRUZ
ELECTRICAL-Rough 6/4/2025 Approved DANIEL DELACRUZ
Excavation/Setback/Form/Re-Bar 6/4/2025 Approved DANIEL DELACRUZ
Floor/Roof Diaphrgm/Shear Wall 6/4/2025 Approved DANIEL DELACRUZ
Footing/Foundation/Slab 6/4/2025 Approved DANIEL DELACRUZ
Insulation 6/4/2025 Corrections Issued DANIEL DELACRUZ
Interior/Exterior Lathing 6/4/2025 Partial Approval DANIEL DELACRUZ
PLUMBING-Rough 6/4/2025 Approved DANIEL DELACRUZ
Shower Pan 6/4/2025 Partial Inspection DANIEL DELACRUZ
HVAC-Rough 6/9/2025 Corrections Issued DANIEL DELACRUZ
HVAC-Rough 6/12/2025 Corrections Issued DANIEL DELACRUZ
Wood Frame 6/18/2025 Not Ready for Inspection DANIEL DELACRUZ
Insulation 6/25/2025 Partial Approval DANIEL DELACRUZ
BUILDING-Rough-Frame 7/21/2025 Approved DANIEL DELACRUZ
Green Building Rough 7/21/2025 Approved DANIEL DELACRUZ
Insulation 7/21/2025 Approved DANIEL DELACRUZ
Final 7/30/2025 Not Ready for Inspection DANIEL DELACRUZ
Green Building Final 7/30/2025 Approved DANIEL DELACRUZ
SGSOV-Seismic Gas S/O Valve 7/30/2025 SGSOV Approved DANIEL DELACRUZ
Smoke Detectors 7/30/2025 Not Ready for Inspection DANIEL DELACRUZ
Final 8/7/2025 Not Ready for Inspection DANIEL DELACRUZ
Smoke Detectors 8/7/2025 Not Ready for Inspection DANIEL DELACRUZ
ELECTRICAL-Final 8/14/2025 Approved DANIEL DELACRUZ
Final 8/14/2025 OK to Issue CofO DANIEL DELACRUZ
HVAC-Final 8/14/2025 Approved DANIEL DELACRUZ
PLUMBING-Final 8/14/2025 Approved DANIEL DELACRUZ
Smoke Detectors 8/14/2025 Approved DANIEL DELACRUZ