5125 E MERIDIAN ST 90042
Certificate Information: 5125 E MERIDIAN ST 90042
- Application / Permit
- 25016-20000-06866
- Plan Check / Job No.
- B25VN06709
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) PATIO COVER TO BED AND BATH, REMODEL KITCHEN, REMOVE AND REPLACE ALL WINDOWS. "COMPLY WITH DEPARTMENT ORDER effective date 02/25/2025. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 4/29/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/15/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 3/15/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 3/19/2025 | APPLICANT |
| Applicant returned to address corrections | 4/10/2025 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 4/25/2025 | ISIS ARGUETA |
| Issued | 4/29/2025 | APPLICANT |
| CofO in Progress | 8/18/2025 | DANIEL DELACRUZ |
| Permit Finaled | 9/15/2025 | DANIEL SANCHEZ |
| CofO Issued | 9/15/2025 | DANIEL SANCHEZ |
| Permit Finaled | 9/15/2025 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/9/2025 | MICHAEL TEMPLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Asprer,, Anjero; Lic. No.: C91126 | 2708 FOOTHILL BLVD. #1006 LA CRESCENTA, CA 91214 |
Inspector Information
| DANIEL DELACRUZ, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO SIERRA, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT MINASSIANS, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/15/2025 | Partial Approval | DANIEL DELACRUZ |
| Deputy Drilled-In Anchors | 6/3/2025 | Conditional Approval | DANIEL DELACRUZ |
| ELECTRICAL-Rough | 6/4/2025 | Approved | DANIEL DELACRUZ |
| Excavation/Setback/Form/Re-Bar | 6/4/2025 | Approved | DANIEL DELACRUZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2025 | Approved | DANIEL DELACRUZ |
| Footing/Foundation/Slab | 6/4/2025 | Approved | DANIEL DELACRUZ |
| Insulation | 6/4/2025 | Corrections Issued | DANIEL DELACRUZ |
| Interior/Exterior Lathing | 6/4/2025 | Partial Approval | DANIEL DELACRUZ |
| PLUMBING-Rough | 6/4/2025 | Approved | DANIEL DELACRUZ |
| Shower Pan | 6/4/2025 | Partial Inspection | DANIEL DELACRUZ |
| HVAC-Rough | 6/9/2025 | Corrections Issued | DANIEL DELACRUZ |
| HVAC-Rough | 6/12/2025 | Corrections Issued | DANIEL DELACRUZ |
| Wood Frame | 6/18/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| Insulation | 6/25/2025 | Partial Approval | DANIEL DELACRUZ |
| BUILDING-Rough-Frame | 7/21/2025 | Approved | DANIEL DELACRUZ |
| Green Building Rough | 7/21/2025 | Approved | DANIEL DELACRUZ |
| Insulation | 7/21/2025 | Approved | DANIEL DELACRUZ |
| Final | 7/30/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| Green Building Final | 7/30/2025 | Approved | DANIEL DELACRUZ |
| SGSOV-Seismic Gas S/O Valve | 7/30/2025 | SGSOV Approved | DANIEL DELACRUZ |
| Smoke Detectors | 7/30/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| Final | 8/7/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| Smoke Detectors | 8/7/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| ELECTRICAL-Final | 8/14/2025 | Approved | DANIEL DELACRUZ |
| Final | 8/14/2025 | OK to Issue CofO | DANIEL DELACRUZ |
| HVAC-Final | 8/14/2025 | Approved | DANIEL DELACRUZ |
| PLUMBING-Final | 8/14/2025 | Approved | DANIEL DELACRUZ |
| Smoke Detectors | 8/14/2025 | Approved | DANIEL DELACRUZ |