6614 N VESPER AVE 91405
Certificate Information: 6614 N VESPER AVE 91405
- Application / Permit
- 25016-20000-06858
- Plan Check / Job No.
- B25VN06698
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF AN (E) 12'-1" X 31'-1" GARAGE W/ UNPERMITTED ADDITION BUILT PRIOR TO JAN 1ST, 2020 TO ACCESSORY DWELLING UNIT PER GCS 65852.23.
- Permit Issued
- Issued on 5/2/2025
- Issuing Office
- Current Status
- CofO Issued on 7/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/15/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 3/15/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 3/17/2025 | APPLICANT |
| Plan Check Approved | 5/2/2025 | GIOVANNY CHAVEZ |
| Issued | 5/2/2025 | APPLICANT |
| CofO in Progress | 7/2/2025 | RYAN SALAZAR |
| Permit Finaled | 7/10/2025 | RUBEN SALAS |
| CofO Issued | 7/10/2025 | RUBEN SALAS |
| Permit Finaled | 7/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/17/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/19/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/19/2025 | LEE GUILBEAUX |
| HPOZ | Cleared | 4/29/2025 | NATHALY DE LA PAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/9/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 5/9/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 5/9/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 5/9/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 5/9/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 6/5/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 6/5/2025 | Corrections Issued | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 6/5/2025 | Approved | RYAN SALAZAR |
| Sewer | 6/5/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 6/12/2025 | Approved | RYAN SALAZAR |
| Green Building Final | 6/12/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 6/12/2025 | Approved | RYAN SALAZAR |
| Final | 6/27/2025 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 6/27/2025 | Approved | RYAN SALAZAR |