20408-20408 1/2 W DEVONSHIRE ST 91311

Certificate Information: 20408-20408 1/2 W DEVONSHIRE ST 91311

Application / Permit
25016-20000-06772
Plan Check / Job No.
B25VN06629
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: CONVERSION OF AN EXISTING ATTACHED 2 CAR GARAGE INTO A NEW JADU GC66323(a)(1) and66333
Permit Issued
Issued on 5/7/2025
Issuing Office
Current Status
CofO Issued on 9/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2025 APPLICANT
Assigned to Plan Check Engineer 3/17/2025 LUISANGEL VALENZUELA
Corrections Issued 3/18/2025 LUISANGEL VALENZUELA
Applicant returned to address corrections 3/29/2025 LUISANGEL VALENZUELA
Applicant returned to address corrections 4/3/2025 LUISANGEL VALENZUELA
Applicant returned to address corrections 4/5/2025 DANIEL YIP
Applicant returned to address corrections 4/15/2025 NEHEMIAS RAMOS
Plan Check Approved 5/6/2025 NEHEMIAS RAMOS
Issued 5/7/2025 APPLICANT
CofO in Progress 8/4/2025 DAVID SCANTLIN
No Progress 9/10/2025 HENRY KIM
CofO in Progress 9/10/2025 HENRY KIM
Permit Finaled 9/16/2025 JOHN JANSON
CofO Issued 9/16/2025 JOHN JANSON
Permit Finaled 9/16/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/24/2025 BRYAN GODINEZ
Sewer availability Cleared 3/24/2025 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 3/27/2025 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/19/2025 Approved DAVID SCANTLIN
PLUMBING-Rough 5/19/2025 Partial Approval DAVID SCANTLIN
ELECTRICAL-Rough 6/10/2025 Approved DAVID SCANTLIN
Green Building Rough 6/10/2025 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 6/10/2025 Approved DAVID SCANTLIN
PLUMBING-Rough 6/10/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 6/13/2025 Approved ARUTYUN MADATYAN
Green Building Rough 6/13/2025 Approved ARUTYUN MADATYAN
Insulation 6/13/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 6/13/2025 Partial Approval ARUTYUN MADATYAN
Drywall Nailing 6/20/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 6/20/2025 Approved ARUTYUN MADATYAN
Shower Pan 6/20/2025 Approved ARUTYUN MADATYAN
Final 7/28/2025 Corrections Issued DAVID SCANTLIN
Green Building Final 7/28/2025 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 7/28/2025 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 7/28/2025 Approved DAVID SCANTLIN
Final 8/1/2025 OK to Issue CofO DAVID SCANTLIN
Special/Order Compliance 8/5/2025 Corrections Issued DAVID SCANTLIN