15147 W SYLVAN ST 91411
Certificate Information: 15147 W SYLVAN ST 91411
- Application / Permit
- 25016-20000-06764
- Plan Check / Job No.
- B25VN06618
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETAHCED GARAGE INTO ACCESSORY DWELLING UNIT PER GC 66323(a)(1). "COMPLY WITH DEPARTMENT ORDER effective date 03/26/2025. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 4/10/2025
- Issuing Office
- Current Status
- CofO Issued on 8/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/14/2025 | ROSENDO MEDINA |
| Corrections Issued | 3/15/2025 | ROSENDO MEDINA |
| Applicant returned to address corrections | 4/3/2025 | ROSENDO MEDINA |
| Plan Check Approved | 4/10/2025 | ROSENDO MEDINA |
| Issued | 4/10/2025 | APPLICANT |
| CofO in Progress | 7/3/2025 | RYAN SALAZAR |
| Permit Finaled | 8/14/2025 | RUBEN SALAS |
| CofO Issued | 8/14/2025 | RUBEN SALAS |
| Permit Finaled | 8/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/19/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/19/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 3/19/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/23/2025 | Approved | DAVID ANDERSON |
| Final | 6/25/2025 | Corrections Issued | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 6/25/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 7/3/2025 | Approved | RYAN SALAZAR |
| Final | 7/3/2025 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 7/3/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 7/3/2025 | Approved | RYAN SALAZAR |
| METHANE-Final | 7/3/2025 | Approved | RYAN SALAZAR |
| METHANE-Rough | 7/3/2025 | Approved | RYAN SALAZAR |
| Smoke Detectors | 7/3/2025 | Approved | RYAN SALAZAR |