9029-9031 W MULBERRY DR 91040

Certificate Information: 9029-9031 W MULBERRY DR 91040

Application / Permit
25016-20000-06739
Plan Check / Job No.
B25VN06577
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1). CONSTRUCTION DESIGN PER ENGR.
Permit Issued
Issued on 3/28/2025
Issuing Office
Valley
Current Status
CofO Issued on 2/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2025 APPLICANT
Assigned to Plan Check Engineer 3/14/2025 HAYATO TSUCHIYA
Corrections Issued 3/15/2025 HAYATO TSUCHIYA
Building Plans Picked Up 3/21/2025 APPLICANT
Plan Check Approved 3/27/2025 GIOVANNY CHAVEZ
Issued 3/28/2025 APPLICANT
CofO in Progress 1/30/2026 NICHOLAS TROWBRIDGE
Permit Finaled 2/20/2026 RUBEN SALAS
CofO Issued 2/20/2026 RUBEN SALAS
Permit Finaled 2/20/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/20/2025 LEE GUILBEAUX
Sewer availability Cleared 3/20/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/20/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/21/2025 LEE GUILBEAUX
Grading Pre-Inspection Cleared 3/27/2025 HAYATO TSUCHIYA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/6/2025 Corrections Issued WILLIAM WREN
PLUMBING-Rough 5/6/2025 Partial Approval WILLIAM WREN
Deputy Drilled-In Anchors 5/7/2025 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 5/8/2025 Approved WILLIAM WREN
Sewer 5/21/2025 Approved WILLIAM WREN
Underground Mechanical 5/21/2025 Approved WILLIAM WREN
ELECTRICAL-Rough 6/5/2025 Corrections Issued WILLIAM WREN
PLUMBING-Rough 6/5/2025 Approved WILLIAM WREN
ELECTRICAL-Rough 6/13/2025 Not Ready for Inspection WILLIAM WREN
HVAC-Rough 6/13/2025 Corrections Issued WILLIAM WREN
BUILDING-Rough-Frame 6/20/2025 Conditional Approval WILLIAM WREN
ELECTRICAL-Rough 6/20/2025 Approved WILLIAM WREN
HVAC-Rough 6/20/2025 Approved WILLIAM WREN
Insulation 6/25/2025 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Corrections Issued LOUIS ESCOTO
Interior/Exterior Lathing 7/2/2025 Approved LOUIS ESCOTO
Drywall Nailing 7/8/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/8/2025 Partial Approval MATTHEW NELSON
Interior/Exterior Lathing 7/22/2025 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/31/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 7/31/2025 Approved WILLIAM WREN
Shower Pan 7/31/2025 Approved WILLIAM WREN
Final 12/26/2025 Corrections Issued NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 1/21/2026 Approved NICHOLAS TROWBRIDGE
Final 1/21/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
Green Building Final 1/21/2026 Approved NICHOLAS TROWBRIDGE
Green Building Rough 1/21/2026 Approved NICHOLAS TROWBRIDGE
METHANE-Final 1/21/2026 Approved NICHOLAS TROWBRIDGE
METHANE-Rough 1/21/2026 Approved NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 1/21/2026 SGSOV Approved NICHOLAS TROWBRIDGE
Smoke Detectors 1/21/2026 Approved NICHOLAS TROWBRIDGE
Final 1/28/2026 OK to Issue CofO NICHOLAS TROWBRIDGE
Service/Power Release 1/28/2026 Approved NICHOLAS TROWBRIDGE