22456-22458 W ROSCOE BLVD 91304

Certificate Information: 22456-22458 W ROSCOE BLVD 91304

Application / Permit
25016-20000-06694
Plan Check / Job No.
B25VN06541
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT IRREG SHAPED PORTION OF SFD TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 3/27/2025
Issuing Office
Valley
Current Status
CofO Issued on 11/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2025 APPLICANT
Assigned to Plan Check Engineer 3/15/2025 JEROME MAGAT PALMA
Corrections Issued 3/15/2025 JEROME MAGAT PALMA
Building Plans Picked Up 3/19/2025 APPLICANT
Plan Check Approved 3/26/2025 SERGIO MUNIZ
Issued 3/27/2025 APPLICANT
CofO in Progress 9/3/2025 JEFFREY HARTLINE
No Progress 9/19/2025 HENRY KIM
CofO in Progress 9/19/2025 HENRY KIM
Permit Finaled 11/4/2025 JOHN JANSON
CofO Issued 11/4/2025 JOHN JANSON
Permit Finaled 11/4/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/19/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 3/19/2025 BIAINA HARITUNIAN
Sewer availability Cleared 3/19/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/4/2025 Approved CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 6/20/2025 Conditional Approval HENRY KIM
Sewer 6/23/2025 Partial Approval ROBERT GOLD
BUILDING-Rough-Frame 7/15/2025 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 7/15/2025 Approved CHRIS CHRISTENSEN
HVAC-Rough 7/15/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 7/15/2025 Approved CHRIS CHRISTENSEN
Sewer 7/15/2025 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 7/15/2025 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 7/31/2025 Approved GEVORK IPCHYAN
Shower Pan 8/6/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 9/3/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Final 9/3/2025 Approved JEFFREY HARTLINE
Final 9/3/2025 OK to Issue CofO JEFFREY HARTLINE
HVAC-Final 9/3/2025 Approved JEFFREY HARTLINE
PLUMBING-Final 9/3/2025 Approved JEFFREY HARTLINE
Service/Power Release 9/3/2025 Approved JEFFREY HARTLINE
Smoke Detectors 9/3/2025 Approved JEFFREY HARTLINE