153 W 52ND ST 90037
Certificate Information: 153 W 52ND ST 90037
- Application / Permit
- 25016-20000-05981
- Plan Check / Job No.
- B25VN05777
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(1).
- Permit Issued
- Issued on 5/20/2025
- Issuing Office
- Current Status
- CofO Issued on 4/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2025 | SERGIO MUNIZ |
| Corrections Issued | 3/13/2025 | SERGIO MUNIZ |
| Plan Check Approved | 5/19/2025 | ROSENDO MEDINA |
| Issued | 5/20/2025 | APPLICANT |
| CofO in Progress | 4/3/2026 | ALEJANDRO DE ARTOLA |
| No Progress | 4/6/2026 | ALEJANDRO DE ARTOLA |
| CofO in Progress | 4/6/2026 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 4/9/2026 | DEROLD HAUFF |
| CofO Issued | 4/9/2026 | DEROLD HAUFF |
| Permit Finaled | 4/9/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/22/2025 | ERIK BEASLEY |
| Sewer availability | Cleared | 3/22/2025 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2025 | ERIK BEASLEY |
| Construction near power lines | Cleared | 5/12/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/29/2025 | Conditional Approval | ANTHONY RAMOS |
| Footing/Foundation/Slab | 6/2/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 7/1/2025 | Corrections Issued | DAVID WILLIAMS |
| PLUMBING-Rough | 7/1/2025 | Corrections Issued | DAVID WILLIAMS |
| ELECTRICAL-Rough | 7/11/2025 | Not Ready for Inspection | ANTHONY RAMOS |
| PLUMBING-Rough | 7/11/2025 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Rough | 7/15/2025 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Rough | 7/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/21/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/1/2025 | Partial Inspection | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/1/2025 | Partial Inspection | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/5/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/5/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 8/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/13/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/20/2025 | Corrections Issued | MICHAEL LEWIS |
| Green Building Rough | 8/20/2025 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Rough | 8/27/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 8/27/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/5/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Wood Frame | 9/5/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/8/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/8/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/9/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/15/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Wood Frame | 9/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 9/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 9/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 10/1/2025 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 10/7/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/8/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/8/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/19/2025 | No Access for Inspection | SABAS ALONSO |
| Green Building Final | 11/19/2025 | No Access for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/19/2025 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 11/19/2025 | No Access for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/25/2025 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/22/2026 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 1/27/2026 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 1/27/2026 | Approved | SABAS ALONSO |
| PLUMBING-Final | 1/27/2026 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 2/4/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/4/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 2/11/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 4/2/2026 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 4/2/2026 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 4/2/2026 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 4/2/2026 | Approved | ALEJANDRO DE ARTOLA |