1439 N PORTIA ST 90026

Certificate Information: 1439 N PORTIA ST 90026

Application / Permit
25016-20000-05928
Plan Check / Job No.
B25VN05700
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1)
Permit Issued
Issued on 4/29/2025
Issuing Office
Valley
Current Status
CofO Issued on 11/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2025 APPLICANT
Assigned to Plan Check Engineer 3/7/2025 ARTIN ZARUKIAN
Corrections Issued 3/8/2025 ARTIN ZARUKIAN
Building Plans Picked Up 3/12/2025 APPLICANT
Issued 4/29/2025 APPLICANT
CofO in Progress 11/17/2025 HAMIK HARTOUNIAN
Permit Finaled 11/18/2025 DEROLD HAUFF
CofO Issued 11/18/2025 DEROLD HAUFF
Permit Finaled 11/18/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/20/2025 JONATHAN HOM
Tenant Habitability Plan Cleared 3/21/2025 RICARDO BOHORQUEZ
Address approval Cleared 4/21/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 4/21/2025 CINDY QI
Sewer availability Cleared 4/21/2025 CINDY QI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/16/2025 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 5/16/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Pre-Inspection 5/16/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 6/2/2025 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/2/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 6/25/2025 Approved WILLIAM SIERRA
Footing/Foundation/Slab 6/25/2025 Approved WILLIAM SIERRA
PLUMBING-Rough 6/25/2025 Partial Approval WILLIAM SIERRA
Underground Mechanical 6/25/2025 Partial Approval WILLIAM SIERRA
ELECTRICAL-Rough 7/15/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 7/15/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/18/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 7/18/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 8/4/2025 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/4/2025 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 8/4/2025 Approved HAMIK HARTOUNIAN
Shower Pan 8/4/2025 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/8/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 8/8/2025 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 8/8/2025 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/18/2025 Partial Approval HAMIK HARTOUNIAN
Special/Order Compliance 8/18/2025 Partial Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/21/2025 Partial Approval HAMIK HARTOUNIAN
Insulation 8/21/2025 Partial Approval HAMIK HARTOUNIAN
Drywall Nailing 8/29/2025 Approved REGINA MENDEZ
Insulation 8/29/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 8/29/2025 Approved REGINA MENDEZ
BUILDING-Rough-Frame 11/10/2025 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 11/10/2025 Corrections Issued HAMIK HARTOUNIAN
Final 11/10/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 11/10/2025 Approved HAMIK HARTOUNIAN
Green Building Rough 11/10/2025 Approved HAMIK HARTOUNIAN
HVAC-Final 11/10/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Final 11/10/2025 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/10/2025 SGSOV Approved HAMIK HARTOUNIAN
Service/Power Release 11/10/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Smoke Detectors 11/10/2025 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 11/13/2025 Approved HAMIK HARTOUNIAN
HVAC-Final 11/13/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Final 11/13/2025 Approved HAMIK HARTOUNIAN
Service/Power Release 11/13/2025 Not Required HAMIK HARTOUNIAN
Final 11/17/2025 OK to Issue CofO HAMIK HARTOUNIAN