- INTERIOR REMODEL TO THE (E) DWELLING UNIT. ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/14/2025
- Issuing Office
- Valley
- Current Status
- Issued on 3/14/2025
Permit Application Status History
| Submitted | 3/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2025 | ARAMIK SHAHMIRZAIAN |
| Corrections Issued | 3/3/2025 | ARAMIK SHAHMIRZAIAN |
| Issued | 3/14/2025 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 3/11/2025 | ANDREA MAGANA-WITHERS |
| Grading Pre-Inspection | Cleared | 3/12/2025 | ALEXANDER HELFER |
Contact Information
| Contractor | Vision Adu Llc; Lic. No.: 1115842-B | 405 S MISSION DR SAN GABRIEL, CA 91776 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/8/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 4/10/2025 | Approved | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 4/10/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 5/2/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 5/2/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 5/2/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 5/5/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 5/5/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 5/5/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 5/8/2025 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 5/8/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 5/13/2025 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 5/16/2025 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 5/19/2025 | Approved | DAVID WILLIAMS |
| Wood Frame | 5/19/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 6/9/2025 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 6/9/2025 | Approved | ALIZAH MAYAGOITIA |
| Sewer | 6/10/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 8/15/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/15/2025 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 8/15/2025 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 8/21/2025 | Approved | GEM DE OCAMPO |
| Insulation | 8/21/2025 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 8/21/2025 | Approved | GEM DE OCAMPO |
| Shower Pan | 8/21/2025 | Approved | GEM DE OCAMPO |
| Final | 10/1/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 10/1/2025 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 10/1/2025 | Approved | ALIZAH MAYAGOITIA |