18921 W KESWICK ST 91335

Certificate Information: 18921 W KESWICK ST 91335

Application / Permit
25016-20000-05737
Plan Check / Job No.
B25VN05502
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: ADDITION AND REMODEL OF (E) SINGLE FAMILY DWELLING. WORK PER ENGINEERED DESIGN. **SEE COMMENTS
Permit Issued
Issued on 4/28/2025
Issuing Office
Current Status
CofO Issued on 10/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2025 APPLICANT
Assigned to Plan Check Engineer 3/3/2025 OMAR GARNICA
Corrections Issued 3/4/2025 OMAR GARNICA
Applicant returned to address corrections 4/7/2025 KAMYAR EMAMI
Plan Check Approved 4/27/2025 OMAR GARNICA
Issued 4/28/2025 APPLICANT
CofO in Progress 9/29/2025 ARUTYUN MADATYAN
Permit Finaled 10/2/2025 MICHAEL PELHAM
CofO Issued 10/2/2025 MICHAEL PELHAM
Permit Finaled 10/2/2025 MICHAEL PELHAM

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/12/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 4/14/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/1/2025 Corrections Issued JUAN ALVARADO
BUILDING-Rough-Frame 5/6/2025 Approved ARUTYUN MADATYAN
Footing/Foundation/Slab 5/6/2025 Approved ARUTYUN MADATYAN
Green Building Rough 5/6/2025 Approved ARUTYUN MADATYAN
Rough-Elec/Plmb/HVAC 5/6/2025 Approved ARUTYUN MADATYAN
Insulation 5/12/2025 Approved ARUTYUN MADATYAN
Drywall Nailing 5/15/2025 Approved SCOTT SOBEL
Interior/Exterior Lathing 5/28/2025 Approved ARUTYUN MADATYAN
Shower Pan 5/28/2025 Approved ARUTYUN MADATYAN
Final 9/12/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Final 9/12/2025 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 9/12/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 9/26/2025 Approved ARUTYUN MADATYAN
Final 9/26/2025 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 9/26/2025 Approved ARUTYUN MADATYAN
HVAC-Final 9/26/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 9/26/2025 Approved ARUTYUN MADATYAN