5401 N GEYSER AVE 91356

Certificate Information: 5401 N GEYSER AVE 91356

Application / Permit
25016-20000-05672
Plan Check / Job No.
B25VN05440
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL OF (E) 2-STORY SFD: RELOCATE KITCHEN, REPLACE (E) WINDOW WITH 18FT WIDE GLASS DOOR, REPLACE (E) GLASS DOOR, CONVERT (E) PANTRY TO SAUNA W/ EXTERIOR ACCESS. ALL WORK IS ON 1ST FLOOR PER ENG'R DESIGN **ePlan**
Permit Issued
Issued on 5/14/2025
Issuing Office
Current Status
Permit Finaled on 10/10/2025

Permit Application Status History

Submitted 3/1/2025 APPLICANT
Assigned to Plan Check Engineer 3/13/2025 NILOOFAR MEHRAIN
Corrections Issued 3/17/2025 NILOOFAR MEHRAIN
Quality Review Completed 3/20/2025 JASON HEALEY
Plan Check Approved 5/12/2025 NILOOFAR MEHRAIN
Issued 5/14/2025 APPLICANT
Permit Finaled 10/9/2025 JOHN KIDWELL

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/24/2025 GERMAN RODRIGUEZ MENDOZA

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21731 VENTURA BLVD SUITE 110      WOODLAND HILLS, CA 91364

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/13/2025 Approved JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 6/13/2025 Approved JOHN KIDWELL
Footing/Foundation/Slab 6/13/2025 Approved JOHN KIDWELL
Deputy Steel/Welding 6/25/2025 Conditional Approval HENRY KIM
BUILDING-Rough-Frame 6/30/2025 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 6/30/2025 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Rough 6/30/2025 Approved JEFFREY HARTLINE
PLUMBING-Rough 6/30/2025 Not Ready for Inspection JEFFREY HARTLINE
Structural Steel Frame 6/30/2025 Approved JEFFREY HARTLINE
Wood Frame 6/30/2025 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 7/8/2025 Approved JON MCHUGH
Interior/Exterior Lathing 7/8/2025 Partial Approval JON MCHUGH
PLUMBING-Rough 7/8/2025 Approved JON MCHUGH
Deputy Steel/Welding 7/9/2025 Partial Approval JOHN KIDWELL
Shower Pan 7/15/2025 Approved JOHN KIDWELL
Interior/Exterior Lathing 7/24/2025 Approved JEFFREY PARD
BUILDING-Rough-Frame 7/25/2025 Approved JON MCHUGH
Wood Frame 7/25/2025 Approved JON MCHUGH
Insulation 7/28/2025 Approved JON MCHUGH
Drywall Nailing 7/30/2025 Approved JOHN KIDWELL
Final 10/9/2025 Permit Finaled JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV Approved JOHN KIDWELL
Smoke Detectors 10/9/2025 Approved JOHN KIDWELL