6054 N KLUMP AVE 91606
Certificate Information: 6054 N KLUMP AVE 91606
- Application / Permit
- 25016-20000-05652
- Plan Check / Job No.
- B25VN05423
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING ATTACHED GARAGE TO BECOME PART OF THE SINGLE FAMILY DWELLING ( NEW BEDROOM AND BATHROOM). NEW ATTACHED PATIO COVER AND STORAGE ROOM.
- Permit Issued
- Issued on 4/18/2025
- Issuing Office
- Current Status
- CofO Issued on 10/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 3/8/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/11/2025 | APPLICANT |
| Applicant returned to address corrections | 4/11/2025 | ROSENDO MEDINA |
| Issued | 4/18/2025 | APPLICANT |
| CofO in Progress | 9/22/2025 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 10/29/2025 | RUBEN SALAS |
| CofO Issued | 10/29/2025 | RUBEN SALAS |
| Permit Finaled | 10/29/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2025 | BRYAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 4/14/2025 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Saiyan,, Shant Yervant; Lic. No.: C93408 | 3344 LARGA AVE LOS ANGELES, CA 90039 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/5/2025 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 5/15/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 5/19/2025 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 5/28/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 5/30/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 5/30/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/27/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 6/27/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 6/27/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 7/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 7/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 7/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/29/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 7/29/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 7/29/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 7/29/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 8/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 8/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/11/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 8/11/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 9/18/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 9/18/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 9/22/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |