7661-7663 N SEDAN AVE 91304

Certificate Information: 7661-7663 N SEDAN AVE 91304

Application / Permit
25016-20000-05502
Plan Check / Job No.
B25VN05232
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan: Convert attached garage into an Accessory Dwelling Unit (ADU) PER GC 66323(A)(1).
Permit Issued
Issued on 3/12/2025
Issuing Office
Current Status
CofO Issued on 11/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2025 APPLICANT
Assigned to Plan Check Engineer 3/5/2025 SUNMIN LEE
Corrections Issued 3/5/2025 SUNMIN LEE
Plan Check Approved 3/12/2025 RICARDO RAMIREZ
Issued 3/12/2025 APPLICANT
CofO in Progress 10/29/2025 CHRIS CHRISTENSEN
Permit Finaled 11/13/2025 JOHN JANSON
CofO Issued 11/13/2025 JOHN JANSON
Permit Finaled 11/13/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/7/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 3/7/2025 BIAINA HARITUNIAN
Sewer availability Cleared 3/7/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 3/10/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/10/2025 LEE GUILBEAUX

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/14/2025 Partial Approval CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 5/15/2025 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 5/16/2025 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/6/2025 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/6/2025 Approved CHRIS CHRISTENSEN
HVAC-Rough 6/6/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 6/6/2025 Approved CHRIS CHRISTENSEN
Pre-Inspection 6/20/2025 Approved JOHN COLEMAN
Green Building Final 6/27/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Insulation 6/27/2025 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/27/2025 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 7/9/2025 Approved CHRIS CHRISTENSEN
Green Building Rough 7/9/2025 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 7/9/2025 Partial Approval CHRIS CHRISTENSEN
Shower Pan 7/9/2025 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/21/2025 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 10/21/2025 Approved CHRIS CHRISTENSEN
Final 10/21/2025 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 10/21/2025 Approved CHRIS CHRISTENSEN
HVAC-Final 10/21/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Final 10/21/2025 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/21/2025 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 10/21/2025 Approved CHRIS CHRISTENSEN
Final 10/28/2025 OK to Issue CofO CHRIS CHRISTENSEN