4623 S SANFORD DR 90230
Certificate Information: 4623 S SANFORD DR 90230
- Application / Permit
- 25016-20000-05215
- Plan Check / Job No.
- B25VN05037
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE & STORAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1).
- Permit Issued
- Issued on 3/21/2025
- Issuing Office
- Current Status
- CofO Issued on 9/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 3/5/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 3/7/2025 | APPLICANT |
| Plan Check Approved | 3/21/2025 | ANGELICA MARTINEZ |
| Issued | 3/21/2025 | APPLICANT |
| CofO in Progress | 9/3/2025 | WILBER ROSALES |
| CofO Issued | 9/4/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/4/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/10/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2025 | DARIN LAM |
| Specific Plan | Cleared | 3/12/2025 | RICHARD WOO |
| Address approval | Cleared | 3/21/2025 | CHRISTINA BRACO |
Contact Information
| Contractor | Greentech Builders Inc; Lic. No.: 999332-B | 360 SOUTH BURNSIDE AVE UNIT 9J LOS ANGELES, CA 90036 |
| Engineer | Southerland,, Richard Charles; Lic. No.: C88965 | 2335 E COLORADO BLVD SUITE 115, # 170 PASADENA, CA 91107 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/18/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Deputy Drilled-In Anchors | 4/21/2025 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 5/12/2025 | Partial Approval | MICHAEL ALLEN |
| ELECTRICAL-Rough | 5/12/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 5/12/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| PLUMBING-Rough | 5/12/2025 | Approved | MICHAEL ALLEN |
| Special/Order Compliance | 5/12/2025 | Corrections Issued | MICHAEL ALLEN |
| ELECTRICAL-Final | 5/14/2025 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 5/14/2025 | Approved | BOBBY KEY |
| Insulation | 5/14/2025 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 5/14/2025 | Partial Approval | BOBBY KEY |
| Sewer | 5/14/2025 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 5/14/2025 | Corrections Issued | BOBBY KEY |
| Underground Mechanical | 5/14/2025 | Conditional Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 5/16/2025 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 5/16/2025 | Partial Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 5/22/2025 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 5/22/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 5/22/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/22/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 7/28/2025 | Approved | WILBER ROSALES |
| Final | 7/28/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Final | 7/28/2025 | Approved | WILBER ROSALES |
| HVAC-Final | 7/28/2025 | Corrections Issued | WILBER ROSALES |
| PLUMBING-Final | 7/28/2025 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 7/28/2025 | SGSOV Approved | WILBER ROSALES |
| Smoke Detectors | 7/28/2025 | Approved | WILBER ROSALES |
| Final | 9/2/2025 | OK to Issue CofO | WILBER ROSALES |
| HVAC-Final | 9/2/2025 | Approved | WILBER ROSALES |