2408 S CLEMENT AVE 90291

Certificate Information: 2408 S CLEMENT AVE 90291

Application / Permit
25016-20000-04970
Plan Check / Job No.
B25VN04730
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) STORAGE/LAUNDRY ROOM TO FULL BATHROOM
Permit Issued
Issued on 2/24/2025
Issuing Office
Current Status
CofO Issued on 5/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2025 APPLICANT
Assigned to Plan Check Engineer 2/24/2025 OMAR GARNICA
Plan Check Approved 2/24/2025 OMAR GARNICA
Issued 2/24/2025 APPLICANT
CofO in Progress 5/5/2025 JESUS RODRIGUEZ
CofO Issued 5/6/2025 RICHARD STEINBACH
Permit Finaled 5/6/2025 RICHARD STEINBACH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/28/2025 Partial Inspection HERBERT GIRON
ELECTRICAL-Rough 3/5/2025 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 3/5/2025 Approved HERBERT GIRON
PLUMBING-Rough 3/5/2025 Approved HERBERT GIRON
ELECTRICAL-Rough 3/10/2025 Not Ready for Inspection JESUS RODRIGUEZ
Insulation 3/10/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 3/10/2025 Approved JESUS RODRIGUEZ
Shower Pan 3/10/2025 Not Ready for Inspection JESUS RODRIGUEZ
Drywall Nailing 3/12/2025 Approved JAYLIN GRAVITTE
Shower Pan 3/12/2025 Approved JAYLIN GRAVITTE
BUILDING-Rough-Frame 4/2/2025 Conditional Approval JESUS RODRIGUEZ
Final 4/2/2025 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 4/2/2025 Approved JESUS RODRIGUEZ
Pre-Inspection 4/8/2025 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Final 4/29/2025 Approved JESUS RODRIGUEZ
Final 4/29/2025 Corrections Issued JESUS RODRIGUEZ
HVAC-Final 4/29/2025 Approved JESUS RODRIGUEZ
PLUMBING-Final 4/29/2025 Approved JESUS RODRIGUEZ
Smoke Detectors 4/29/2025 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 5/5/2025 Approved JESUS RODRIGUEZ
Final 5/5/2025 OK to Issue CofO JESUS RODRIGUEZ