8818 N GERALD AVE 91343

Certificate Information: 8818 N GERALD AVE 91343

Application / Permit
25016-20000-04928
Plan Check / Job No.
B25VN04707
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Detached garage into an Accessory Dwelling Unit Conversion per state and GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 4/16/2025
Issuing Office
Current Status
CofO Issued on 10/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2025 APPLICANT
Assigned to Plan Check Engineer 2/28/2025 ZAW HAN
Corrections Issued 3/3/2025 ZAW HAN
Plan Check Approved 4/14/2025 ADAM HEGAZI
Issued 4/16/2025 APPLICANT
CofO in Progress 10/28/2025 GAREN HAYRAPETYAN
Permit Finaled 10/29/2025 RUBEN SALAS
CofO Issued 10/29/2025 RUBEN SALAS
Permit Finaled 10/29/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/3/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 3/3/2025 DAVID LOPEZ
Sewer availability Cleared 3/3/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 3/4/2025 DAVID LOPEZ
Construction near power lines Cleared 4/8/2025 GEVORK KARAPETYAN
Construction within easement Cleared 4/8/2025 GEVORK KARAPETYAN

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor L E A D Enterprises Inc; Lic. No.: 955824-B       ,
Contractor Pearl Remodeling; Lic. No.: 955824-B       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/19/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 5/19/2025 Approved KEVIN BERBERYAN
Underground Mechanical 5/28/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 6/26/2025 Partial Approval GAREN HAYRAPETYAN
ELECTRICAL-Rough 6/26/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 6/26/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 6/26/2025 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Rough 6/26/2025 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 7/1/2025 Partial Approval MICHAEL CORTEZ
Insulation 7/1/2025 Partial Approval MICHAEL CORTEZ
BUILDING-Rough-Frame 7/7/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 7/7/2025 Not Ready for Inspection SALVADOR MARTINEZ
Interior/Exterior Lathing 7/7/2025 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 7/10/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Green Building Rough 7/10/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 7/10/2025 Partial Approval NICHOLAS TROWBRIDGE
HVAC-Rough 7/15/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 7/17/2025 Approved GAREN HAYRAPETYAN
Insulation 7/21/2025 Partial Approval SALVADOR MARTINEZ
Drywall Nailing 7/25/2025 Approved SALVADOR MARTINEZ
Insulation 7/25/2025 Approved SALVADOR MARTINEZ
Shower Pan 7/25/2025 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 7/30/2025 Approved MICHAEL CORTEZ
BUILDING-Rough-Frame 9/15/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 9/15/2025 Approved GAREN HAYRAPETYAN
Final 9/15/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 9/15/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 9/15/2025 Approved GAREN HAYRAPETYAN
HVAC-Final 9/15/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Final 9/15/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 9/15/2025 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 9/15/2025 Approved GAREN HAYRAPETYAN
Final 10/28/2025 OK to Issue CofO GAREN HAYRAPETYAN