162-166 1/4 W 65TH ST 90003
Certificate Information: 162-166 1/4 W 65TH ST 90003
- Application / Permit
- 25016-20000-04786
- Plan Check / Job No.
- B25VN04452
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT EXISTING ATTACHED 4-CAR GARAGES (780 SF) AND PORTION OF STORAGE (86 SF) INTO A NEW ACCESSORY DWELLING UNIT (866 SF) PER GCS 65852.2(e)(1)(A). DUPLEX ABOVE TO REMAIN. WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 6/13/2025
- Issuing Office
- Current Status
- CofO Issued on 5/22/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2025 | SERGIO MUNIZ |
| Corrections Issued | 2/25/2025 | SERGIO MUNIZ |
| Applicant returned to address corrections | 3/5/2025 | MADISON ODELL |
| Applicant returned to address corrections | 4/29/2025 | MOHAMMAD ESMAILI |
| Plan Check Approved | 5/6/2025 | SERGIO MUNIZ |
| Issued | 6/13/2025 | APPLICANT |
| CofO Issued | 5/22/2026 | DEROLD HAUFF |
| Permit Finaled | 5/22/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/3/2025 | WALLIE JONG |
| Sewer availability | Cleared | 3/3/2025 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2025 | WALLIE JONG |
| Construction near power lines | Cleared | 4/25/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Sharp Builders & Son; Lic. No.: 1058253-B | , |
| Engineer | Samadzadeh,, Hooman Ali; Lic. No.: NA87661 | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 6/27/2025 | No Access for Inspection | RONNIE MEDINA |
| Deputy Drilled-In Anchors | 7/3/2025 | Approved | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 7/3/2025 | Approved | JOHN QUINTANILLA |
| Sewer | 7/3/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 7/25/2025 | Approved | WAYNE REGESTER |
| HVAC-Rough | 7/25/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Rough | 7/25/2025 | Approved | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 7/31/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 7/31/2025 | Approved | LUIS CASTRO |
| Deputy Wood Construction | 8/4/2025 | Conditional Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 8/7/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Rough | 8/7/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 8/11/2025 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2025 | Partial Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 8/13/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 8/13/2025 | Approved | LUIS CASTRO |
| Insulation | 8/13/2025 | Corrections Issued | LUIS CASTRO |
| Interior/Exterior Lathing | 8/13/2025 | Partial Approval | LUIS CASTRO |
| Insulation | 8/14/2025 | Approved | RONNIE MEDINA |
| Drywall Nailing | 8/20/2025 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 8/20/2025 | Not Ready for Inspection | JOSH MEISTER |
| Shower Pan | 8/20/2025 | Not Ready for Inspection | JOSH MEISTER |
| Interior/Exterior Lathing | 8/22/2025 | Approved | ANTHONY RAMOS |
| Shower Pan | 8/22/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 8/25/2025 | Approved | STUART CHAPMAN |
| Final | 11/12/2025 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Final | 11/12/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 11/12/2025 | SGSOV Approved | JOHN QUINTANILLA |
| Smoke Detectors | 11/12/2025 | Approved | JOHN QUINTANILLA |
| Final | 12/8/2025 | Conditional Approval | LUIS CASTRO |
| Green Building Final | 12/8/2025 | Approved | LUIS CASTRO |
| Final | 1/13/2026 | Corrections Issued | JOHN QUINTANILLA |
| Final | 1/16/2026 | Partial Inspection | JOHN QUINTANILLA |
| Final | 1/22/2026 | Conditional Approval | JOHN QUINTANILLA |