1005-1009 W 46TH ST 90037

Certificate Information: 1005-1009 W 46TH ST 90037

Application / Permit
25016-20000-04773
Plan Check / Job No.
B25VN04434
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
EPLAN: CONVERT (E) ATTACHED STORAGE ROOM TO (N) ACCESSORY DWELLING UNIT PER GC 66323(a)(3).
Permit Issued
Issued on 4/24/2025
Issuing Office
Current Status
CofO Issued on 11/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2025 APPLICANT
Assigned to Plan Check Engineer 2/25/2025 OMAR GARNICA
Corrections Issued 2/26/2025 OMAR GARNICA
Plan Check Approved 3/28/2025 ALEC MOUSAKHANIAN
Issued 4/24/2025 APPLICANT
CofO in Progress 11/17/2025 ALFREDO LOPEZ
Permit Finaled 11/17/2025 ERNESTO CORRAL
CofO Issued 11/17/2025 ERNESTO CORRAL
Permit Finaled 11/17/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 3/7/2025 TAL SHEMEN
Sewer availability Cleared 3/7/2025 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 3/10/2025 TAL SHEMEN

Contact Information

Contractor Elm Construction; Lic. No.: 1099704-B       ,
Contractor Elm Group La Inc; Lic. No.: 1099704-B       ,

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/28/2025 Not Ready for Inspection ALFREDO LOPEZ
Footing/Foundation/Slab 5/27/2025 Partial Approval ALFREDO LOPEZ
Green Building Rough 5/27/2025 Not Ready for Inspection ALFREDO LOPEZ
Interior/Exterior Lathing 5/27/2025 Not Ready for Inspection ALFREDO LOPEZ
Green Building Rough 6/10/2025 Partial Approval ALFREDO LOPEZ
Insulation 6/10/2025 Partial Approval ALFREDO LOPEZ
Wood Frame 6/10/2025 Partial Approval ALFREDO LOPEZ
Insulation 6/11/2025 Approved DARRYL ARNOLD
Insulation 6/12/2025 Approved DARRYL ARNOLD
Drywall Nailing 7/7/2025 No Access for Inspection ALFREDO LOPEZ
Drywall Nailing 7/9/2025 Approved TIMOTHY POWELL
Interior/Exterior Lathing 7/30/2025 Approved ALFREDO LOPEZ
Final 10/30/2025 Not Ready for Inspection ALFREDO LOPEZ
Green Building Final 10/30/2025 Approved ALFREDO LOPEZ
Green Building Rough 10/30/2025 Approved ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 10/30/2025 SGSOV Not Ready ALFREDO LOPEZ
Smoke Detectors 10/30/2025 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 10/30/2025 Approved ALFREDO LOPEZ
Final 11/6/2025 OK to Issue CofO ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 11/6/2025 SGSOV Approved ALFREDO LOPEZ
Smoke Detectors 11/6/2025 Approved ALFREDO LOPEZ