13328 W TERRA BELLA ST 91331

Certificate Information: 13328 W TERRA BELLA ST 91331

Application / Permit
25016-20000-04056
Plan Check / Job No.
B25VN03781
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING 16' X 26' REC ROOM TO NEW DWELLING UNIT PER SB9; EQUIPPED WITH NFPA 13D FIRE SPRINKLERS THROUGHOUT ( ATTACHED STORAGE AND GARAGE TO REMAIN)
Permit Issued
Issued on 8/19/2025
Issuing Office
Valley
Current Status
CofO Issued on 7/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2025 APPLICANT
Assigned to Plan Check Engineer 3/6/2025 EDWARD MEHRABIAN
Corrections Issued 3/11/2025 EDWARD MEHRABIAN
Building Plans Picked Up 3/14/2025 APPLICANT
Quality Review Completed 4/8/2025 DAWN MC NULTY
Applicant returned to address corrections 7/16/2025 EDWARD MEHRABIAN
Plan Check Approved 8/19/2025 SELLA BENYAMIN
Issued 8/19/2025 APPLICANT
CofO in Progress 5/5/2026 MICHEL ABAJAN
CofO Issued 7/8/2026 RUBEN SALAS
Permit Finaled 7/8/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/11/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/11/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/18/2025 LEE GUILBEAUX
Sewer availability Cleared 3/18/2025 LEE GUILBEAUX
Construction near power lines Cleared 4/23/2025 GEVORK KARAPETYAN
Clean Up Green Up Cleared 5/5/2025 DORIAN AGUILAR
Senate Bill 9 Cleared 5/5/2025 DORIAN AGUILAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/15/2025 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 11/19/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 2/12/2026 Approved MICHEL ABAJAN
HVAC-Rough 2/12/2026 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/26/2026 Approved MICHEL ABAJAN
Drywall Nailing 3/26/2026 Approved MICHEL ABAJAN
ELECTRICAL-Final 3/26/2026 Approved MICHEL ABAJAN
Final 3/26/2026 Corrections Issued MICHEL ABAJAN
Green Building Final 3/26/2026 Approved MICHEL ABAJAN
Green Building Rough 3/26/2026 Approved MICHEL ABAJAN
HVAC-Final 3/26/2026 Approved MICHEL ABAJAN
PLUMBING-Final 3/26/2026 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/26/2026 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 3/26/2026 Corrections Issued MICHEL ABAJAN
Final 5/4/2026 OK to Issue CofO MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/4/2026 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 5/4/2026 Approved MICHEL ABAJAN