13140 W APPLETON WAY 90066

Certificate Information: 13140 W APPLETON WAY 90066

Application / Permit
25016-20000-04026
Plan Check / Job No.
B25VN03731
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1)
Permit Issued
Issued on 3/28/2025
Issuing Office
Current Status
CofO Issued on 1/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2025 APPLICANT
Assigned to Plan Check Engineer 2/21/2025 JEROME MAGAT PALMA
Corrections Issued 2/21/2025 JEROME MAGAT PALMA
Plan Check Approved 3/28/2025 GIOVANNY CHAVEZ
Issued 3/28/2025 APPLICANT
CofO in Progress 1/5/2026 MICHAEL ALLEN
Permit Finaled 1/5/2026 RICHARD STEINBACH
CofO Issued 1/5/2026 RICHARD STEINBACH
Permit Finaled 1/5/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 2/28/2025 LEE GUILBEAUX
Sewer availability Cleared 2/28/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 2/28/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/4/2025 LEE GUILBEAUX
Specific Plan Cleared 3/24/2025 RICHARD WOO

Contact Information

Contractor Villa Remodeling & Painting Inc; Lic. No.: 1075941-B 21700 OXNARD ST   SUITE 1760    WOODLAND HILLS, CA 91367
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/16/2025 Approved MICHAEL ALLEN
Sewer 6/16/2025 Approved MICHAEL ALLEN
ELECTRICAL-Rough 7/14/2025 Approved MICHAEL ALLEN
Green Building Rough 7/14/2025 Not Ready for Inspection MICHAEL ALLEN
HVAC-Rough 7/14/2025 Partial Approval MICHAEL ALLEN
PLUMBING-Rough 7/14/2025 Approved MICHAEL ALLEN
Special/Order Compliance 7/14/2025 Corrections Issued MICHAEL ALLEN
HVAC-Rough 7/31/2025 Not Ready for Inspection WILBER ROSALES
Insulation 7/31/2025 Corrections Issued WILBER ROSALES
Interior/Exterior Lathing 7/31/2025 Partial Approval WILBER ROSALES
HVAC-Rough 8/4/2025 Not Ready for Inspection WILBER ROSALES
Insulation 8/4/2025 Not Ready for Inspection WILBER ROSALES
BUILDING-Rough-Frame 8/8/2025 Approved WILBER ROSALES
Green Building Rough 8/8/2025 Approved WILBER ROSALES
HVAC-Rough 8/8/2025 Approved WILBER ROSALES
Insulation 8/13/2025 Approved WILBER ROSALES
Drywall Nailing 8/25/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 9/3/2025 Approved WILBER ROSALES
Final 11/21/2025 Corrections Issued STEPHANIE SWANSON
Green Building Final 11/21/2025 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 11/21/2025 SGSOV Not Required STEPHANIE SWANSON
Smoke Detectors 11/21/2025 Approved STEPHANIE SWANSON
Final 12/1/2025 No Access for Inspection KENNETH NAGLE
Final 12/3/2025 Not Ready for Inspection WILBER ROSALES
ELECTRICAL-Final 1/2/2026 Approved MICHAEL ALLEN
Final 1/2/2026 OK to Issue CofO MICHAEL ALLEN
HVAC-Final 1/2/2026 Approved MICHAEL ALLEN
PLUMBING-Final 1/2/2026 Approved MICHAEL ALLEN