913 E 83RD ST 90001
Certificate Information: 913 E 83RD ST 90001
- Application / Permit
- 25016-20000-03683
- Plan Check / Job No.
- B25VN03392
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan - Convert an existing garage to an ADU per state law with Construction of a new porch. work per WFPP
- Permit Issued
- Issued on 9/21/2025
- Issuing Office
- Current Status
- Issued on 9/21/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2025 | NGHI SU |
| Corrections Issued | 2/24/2025 | NGHI SU |
| Applicant returned to address corrections | 8/16/2025 | NGHI SU |
| Plan Check Approved | 9/12/2025 | NGHI SU |
| Issued | 9/21/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/15/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 7/15/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 7/15/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 10/10/2025 | Corrections Issued | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 10/16/2025 | Partial Approval | JOHN QUINTANILLA |
| Sewer | 10/16/2025 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/24/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 10/28/2025 | Partial Approval | LUIS CASTRO |
| Footing/Foundation/Slab | 10/29/2025 | Partial Inspection | JOHN QUINTANILLA |
| Sewer | 10/29/2025 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 11/13/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 11/13/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Sewer | 11/13/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 11/19/2025 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 1/29/2026 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 1/29/2026 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 1/29/2026 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 2/11/2026 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 2/11/2026 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 2/11/2026 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 3/13/2026 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 4/1/2026 | Approved | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 4/1/2026 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 4/10/2026 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Rough | 4/10/2026 | Approved | JOHN QUINTANILLA |
| Insulation | 4/10/2026 | Conditional Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2026 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 4/23/2026 | Approved | JOHN QUINTANILLA |
| Shower Pan | 5/4/2026 | Approved | ALEX COLIN |
| Final | 5/26/2026 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Final | 5/26/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 5/26/2026 | SGSOV Approved | JOHN QUINTANILLA |
| Smoke Detectors | 5/26/2026 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Final | 5/27/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Final | 5/27/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Final | 5/27/2026 | Not Ready for Inspection | JOHN QUINTANILLA |