6751 N FALLBROOK AVE 91307
Certificate Information: 6751 N FALLBROOK AVE 91307
- Application / Permit
- 25016-20000-03553
- Plan Check / Job No.
- B25VN03263
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Grocery Store
- Work Description
- EPLAN TENANT IMPROVEMENT TO (E) GROCERY STORE AND INSTALL NEW ROOFTOP EQUIPMENT
- Permit Issued
- Issued on 10/7/2025
- Issuing Office
- Current Status
- Permit Finaled on 3/5/2026
Permit Application Status History
| Submitted | 2/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2025 | RAPHAEL ROSAS |
| Assigned to Zoning Architect | 2/27/2025 | LY CHEA |
| Corrections Issued | 3/5/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 3/6/2025 | STEVEN KIM |
| Applicant returned to address corrections | 6/27/2025 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 7/17/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 10/7/2025 | RAPHAEL ROSAS |
| Issued | 10/7/2025 | APPLICANT |
| Permit Finaled | 3/4/2026 | BRIAN KELLY |
Permit Application Clearance Information
| Miscellaneous | Cleared | 3/25/2025 | RICARDO MARTINEZ |
| Green Code | Cleared | 7/11/2025 | MICHAEL AYERS |
| DAS Clearance | Cleared | 9/24/2025 | Ricardo Ramirez Solis |
| Zoning Plan Check | Cleared | 9/29/2025 | LY CHEA |
Contact Information
| Architect | Sargenti,, Robert Jon; Lic. No.: NA31054 | , |
| Contractor | Harco Group Inc; Lic. No.: 842851-B | , |
| Contractor | Mal-Wal Of Southern California Inc; Lic. No.: 842851-B | , |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 10/9/2025 | Not Ready for Inspection | BRIAN KELLY |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | Partial Inspection | BRIAN KELLY |
| Wood Frame | 10/9/2025 | Partial Inspection | BRIAN KELLY |
| Drywall Nailing | 10/11/2025 | Partial Approval | BRIAN KELLY |
| Deputy Drilled-In Anchors | 10/15/2025 | Conditional Approval | BRIAN KELLY |
| Deputy Reinf. Concrete | 10/15/2025 | Conditional Approval | BRIAN KELLY |
| Drywall Nailing | 10/15/2025 | Partial Approval | BRIAN KELLY |
| T-Bar Ceiling | 10/15/2025 | Not Ready for Inspection | BRIAN KELLY |
| T-Bar Ceiling | 10/17/2025 | Approved | BRIAN KELLY |
| Light Gage Steel Frame | 10/27/2025 | Not Ready for Inspection | BRIAN KELLY |
| Deputy Drilled-In Anchors | 10/28/2025 | Conditional Approval | BRIAN KELLY |
| Drywall Nailing | 10/30/2025 | Approved | BRIAN KELLY |
| Light Gage Steel Frame | 11/7/2025 | Not Ready for Inspection | BRIAN KELLY |
| Light Gage Steel Frame | 11/10/2025 | Approved | SCOTT SOBEL |
| Final | 11/20/2025 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Final | 11/20/2025 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 11/20/2025 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 11/20/2025 | Not Ready for Inspection | BRIAN KELLY |
| Final | 12/18/2025 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Final | 12/18/2025 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 12/18/2025 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 12/18/2025 | Not Ready for Inspection | BRIAN KELLY |
| Final | 1/5/2026 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Final | 1/5/2026 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 1/5/2026 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 1/5/2026 | Not Ready for Inspection | BRIAN KELLY |
| Final | 3/4/2026 | Permit Finaled | BRIAN KELLY |
| Green Building Final | 3/4/2026 | Approved | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 3/4/2026 | SGSOV Approved | BRIAN KELLY |
| Smoke Detectors | 3/4/2026 | Approved | BRIAN KELLY |